During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
---
- The team member working on it estimates seven days.
What value (in days) should be used for planning?
Correct Answer: A
A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time.
What would be the elapsed time required to complete the Story?
Correct Answer: A