The planning for NEWGEN has started
-ZYXS will be the service integrator
-OUTSCO will provide application support services
-NETSCO will provide network services.
-PAYSCO is asked to continue to provide payroll services
Users are happy with the services of PAYSCO The contract with PAYSCO has 2 years left to run This is 18 months after the expected completion date ot the implementation of the SIAM model Initial discussions by ZYXS with PAYSCO have indicated that PAYSCO does not want to make any contract changes to support the SIAM model.
Given this constraint what is most likely to be the best method to plan for onboarding PAYSCO?
ZYX has decided to create an internal service provider for application development and support This new service provider is formed by merging relevant staff from every ZYX company with the necessary capabilities and skills.
This internal service provider will operate from multiple locations, which enables the provision of year-round
24-hour support.
A capability framework for application development and support is drawn up for the new internal service provider What will the development of the capability framework help to address?
Project NEWGEN is in the Implementation stage. OUTSCO and ZYXD are service providers. ZYXD is still managed by ZYXS.
Services provided by OUTSCO and ZYXD are not performing as expected due to poor conformance with expected processes and behaviors.
What are the most important activities to resolve performance issues?
The ZYX Board of Directors decided that the proposal from SIAMRUS for ZYXUK was not suitable to be used for the whole of the group, and asked the ZYXS IT Director to lead the creation of a new SIAM strategy.
This new SIAM strategy has now been approved by the NEWGEN Executive Steering Board.
What is the best approach to ensure that the ZYXUK Management Board supports the implementation of this SIAM Strategy?
One year ago. OUTSCO was appointed as the service integrator for ZYX. ZYXH provides the retained capabilities.
After a year of operating the SIAM model, OUTSCO has noticed that the 99 5% availability service level target for NEWBNK has been consistently overachieved by 0.4% every month.
In order to provide better value to ZYX and to challenge the service providers in their delivery, ZYXH would like to increase the availability target to 99 9% as soon as possible.
What is the best way of doing this?