- Home
- Microsoft Certification
- 070-348 Exam
- Microsoft.070-348.dumpsfiles Dumps
Free Microsoft 070-348 Exam Dumps Questions & Answers
| Exam Code/Number: | 070-348Join the discussion |
| Exam Name: | Managing Projects and Portfolios with Microsoft PPM |
| Certification: | Microsoft |
| Question Number: | 48 |
| Publish Date: | Oct 12, 2026 |
|
Rating
100%
|
|
Total 48 questions
This question requires that you evaluate the underlined text to determine if it is correct.
To review the resource engagements requested by a project manager, the resource manager can navigate to the Resource Requests page and accept or reject the requests.
Review the underlined text. If it makes the statement correct, select "No change is needed."
If the statement is incorrect, select the answer choice that makes the statement correct.
You are a resource manager in an organization that uses Microsoft PPM for resource management. You manage two teams, one local and one remote. Project managers are instructed to always submit resource requests based on generic roles instead of named resources. Resource managers replace the generic resources with available named resources.
Project managers must not start work on projects that have generic resources assigned.
You need to replace proposed requests with committed, named resources.
Which three actions should you perform? Each correct answer presents part of the solution.
You are a project manager in an organization that uses Microsoft PPM.
You have been given additional responsibilities managing existing projects created by another project manager.
When reviewing the project plan, you observe that some of the upcoming tasks are assigned to a generic resource.
You need to update the generic tasks to use defined resources.
Which type of resource should you use?
You are a portfolio manager for an organization that uses Microsoft PPM to manage projects. You plan to implement Power BI.
You need to import into Power BI by using the Microsoft Project Online content pack.
What should you do?
DRAG DROP
You are a product manager in an organization that is using Microsoft PPM.
Some of your resources update their assignments correctly.
You need to accept their updates without review by setting up an approval rule.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
