You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Enterprise Gantt Chart is visible to all project managers.
You plan to create a new project enterprise custom field to show information about schedule variance.
You need to include this new field in the Enterprise Gantt Chart in Project Professional 2013 so that all project managers of actual and future projects who use this view can see this field by default.
What should you do?
You are a project manager for an organization that uses Project Server 2013. You and other project managers use Project Professional 2013 to manage projects.
The resources on your project are overallocated due to work assigned across the enterprise. As a result, some work on your project does not finish as scheduled. Some tasks are left partially complete. Other tasks did not start at all.
You need to resolve this issue.
What should you do?
Your work in a multinational corporation which uses Project Server 2013 to plan and control projects in different business units. Each business unit has its own portfolio of projects but can participate in strategic projects. The Project Management Office (PMO) has configured
Enterprise Project Types (EPTs) to create new products, launch marketing campaigns, and deploy new lines of business tools to comply with the governance processes.
One of your roles is to identify new products. A local team in Singapore produces an effective idea for a new product.
You need to create a business case for the next portfolio analysis. You need to gather general information about the new product by efficiently collaborating with the local team.
What should you do?
You are a program manager for an organization that uses Project Server 2013.
You are responsible for implementing a data warehouse that compiles relational data from many business areas. Your project managers need to be able to manage the implementation for a business area as separate projects, while still recognizing the dependencies at a program level.
You need to maintain ownership and authority of key program dates at the program level.
What should you do?
You are a project manager who uses Project Server 2013.
You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.
You need to replace this resource with a newly-hired resource.
What should you do?