- Home
- Oracle Certification
- 1Z1-1075 Exam
- Oracle.1Z1-1075.dumpsfiles Dumps
Free Oracle 1Z1-1075 Exam Dumps Questions & Answers
| Exam Code/Number: | 1Z1-1075Join the discussion |
| Exam Name: | Oracle Manufacturing and Maintenance Cloud 2019 Implementation Essentials |
| Certification: | Oracle |
| Question Number: | 65 |
| Publish Date: | Aug 31, 2026 |
|
Rating
100%
|
|
Total 65 questions
A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is
assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given
work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?
A Work Center created a month ago is no longer in use now. You want to remove the Work Center; however,
the system is no allowing you to delete it.
Identify three reasons for this.
Your customer has multiple distribution centers and a few manufacturing plants. Plants make different items
with some overlap between them in terms of products manufactured. The distribution centers stock parts from
all plants. A Corporate Engineering team is responsible for centrally defining items and catalogues. This team
defines the items and sets the attributes for most parameters. The respective distribution centers and
manufacturing plants are allowed to change some attributes locally.
Identify two different ways of achieving this requirement.
Identify the two capabilities that the Application Development Framework Desktop Integration (ADFDI)
framework provides for Work Definitions in Manufacturing Cloud.
Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is
assigned to the work center W1. There are five units of LATHE available, of which three units are available
for the Morning Shift and the remaining units are available for the Evening Shits.
Which two actions must you perform to associate LATHE with W1?