You are reviewing the production status of your manufacturing plant shop floor as a production supervisor. Your production manager wants a report on a work order status which is reserved against a particular customer. The final assembly of the work order is serialized.
Which option shows the steps to complete the task using the mobile application?
An order entry specialist creates a Back-to-Back order for product item with an intention of fulfilling by in-house manufacturing. The fulfillment line is scheduled and Supply Chain Orchestration (SCO) has initiated creation of a Supply Order rather than Work Order.
Identify two options that can cause this situation.
Your customer plans to use Oracle Representational State Transfer (REST) API with Oracle Supply Chain Management Cloud (Oracle SCM Cloud) to support integration requirements.
Identify four REST resources and the corresponding HTTP action available with Manufacturing Cloud.
In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
A plant operates three continuous daily shifts of eight hours each for five days in a week.
One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.