The project manager for the Customer Processes Project has heard a rumour that Web 'n' Go is having financial difficulties. If this company becomes bankrupt, they will not be able to supply the agreed customer web-based portal services which are required to enable the single customer services call centre. The programme manager has added this risk to the programme risk register.
Is this action by the programme manager an appropriate application of the 'design' theme, and why?
Which of following is False?
The programme is in the middle of Tranche 2 and a new SRO has been appointed. In order to understand the current status of the programme, the SRO has asked for a health check to be carried out. The health check was not in the assurance plan, and there is no budget available to pay for an external auditor. As a result, the programme manager has agreed with the SRO that a senior member of the portfolio office, who is acting as the programme office lead, should complete the health check instead.
How well does this action by the programme manager apply the 'assurance' theme, and why?
Which of the following statements best defines 'MSP Principles'?
Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

Explanation:
Action
Role
Provide expertise in UU's programme scheduling software
Programme office lead
Develop the process for procuring external trainers
Programme manager
Approve the process for assigning internal staff to the programme
Senior responsible owner
The Programme Office provides the technical "best practice" and tool expertise (scheduling software). The Programme Manager designs the management processes for delivery (procurement). The SRO approves the overarching governance and resource allocation rules.