Question 1/18
Which drawback of Waterfall is addressed in Agile methodology?
Correct Answer: B
The Waterfall methodology is a linear approach where requirements are defined upfront, and changes are difficult to accommodate once the project begins. Agile methodology , on the other hand, emphasizes flexibility and adaptability to changing requirements.
Key Considerations:
Inherent Uncertainty in Cost: While cost uncertainty exists in both methodologies, Agile does not specifically address this drawback of Waterfall.
Inflexibility to Changing Requirements: Waterfall's rigid structure makes it difficult to incorporate changes once the project starts. Agile addresses this by allowing iterative development and continuous feedback.
Capturing All Requirements Upfront: Agile does not aim to capture all requirements upfront; instead, it embraces evolving requirements throughout the project.
Stakeholder Agreement on Scope Before Work Begins: Agile encourages ongoing collaboration with stakeholders rather than requiring scope agreement upfront.
Evaluation of Each Option:
A . The agile methodology addresses the inherent uncertainty in cost associated with waterfall:
Agile does not specifically address cost uncertainty.
Conclusion: This is not correct .
B . Agile development addresses the inflexibility of waterfall as it pertains to changing requirements:
This is the primary drawback of Waterfall that Agile addresses through its iterative and flexible approach.
Conclusion: This is correct .
C . The agile methodology captures all requirements at the start of a project to reduce risks typically experienced in waterfall:
Agile does not capture all requirements upfront; it embraces evolving requirements.
Conclusion: This is not correct .
D . Agile development requires stakeholders to agree to the scope of the project before the work begins, reducing uncertainty in the design:
Agile does not require upfront scope agreement; it promotes adaptive planning.
Conclusion: This is not correct .
Final Recommendation:
The drawback of Waterfall addressed in Agile is:
B . Agile development addresses the inflexibility of waterfall as it pertains to changing requirements.
Key Considerations:
Inherent Uncertainty in Cost: While cost uncertainty exists in both methodologies, Agile does not specifically address this drawback of Waterfall.
Inflexibility to Changing Requirements: Waterfall's rigid structure makes it difficult to incorporate changes once the project starts. Agile addresses this by allowing iterative development and continuous feedback.
Capturing All Requirements Upfront: Agile does not aim to capture all requirements upfront; instead, it embraces evolving requirements throughout the project.
Stakeholder Agreement on Scope Before Work Begins: Agile encourages ongoing collaboration with stakeholders rather than requiring scope agreement upfront.
Evaluation of Each Option:
A . The agile methodology addresses the inherent uncertainty in cost associated with waterfall:
Agile does not specifically address cost uncertainty.
Conclusion: This is not correct .
B . Agile development addresses the inflexibility of waterfall as it pertains to changing requirements:
This is the primary drawback of Waterfall that Agile addresses through its iterative and flexible approach.
Conclusion: This is correct .
C . The agile methodology captures all requirements at the start of a project to reduce risks typically experienced in waterfall:
Agile does not capture all requirements upfront; it embraces evolving requirements.
Conclusion: This is not correct .
D . Agile development requires stakeholders to agree to the scope of the project before the work begins, reducing uncertainty in the design:
Agile does not require upfront scope agreement; it promotes adaptive planning.
Conclusion: This is not correct .
Final Recommendation:
The drawback of Waterfall addressed in Agile is:
B . Agile development addresses the inflexibility of waterfall as it pertains to changing requirements.
Add Comments
- Other Question (18q)
- Q1. Which drawback of Waterfall is addressed in Agile methodology?...
- Q2. Which auxiliary service supplements all of the services in the Business Analysis Service F...
- Q3. When used for business analysis, what does a process model show?...
- Q4. What is a purpose of Agile requirements validation?...
- Q5. At a recent Board Meeting the Directors of an office fitting company ratified the company'...
- Q6. What is the first step in the gap analysis process?...
- Q7. Which technique uses an iterative approach to uncover innovative options?...
- Q8. Which generic business improvement strategy involves eliminating redundant tasks?...
- Q9. The management of a chain of hotels has decided that one of its critical success factors (...
- Q10. Which of the following statements about the scenario analysis investigation technique is F...
- Q11. At a recent Board Meeting the Directors of an office fitting company ratified the company'...
- Q12. What does the position of stakeholders on a power/interest grid represent?...
- Q13. In requirements management, what is change control?...
- Q14. AlpmeTrails is a company that specialises in offering tailored walking holidays The compan...
- Q15. On a business process model, how are hand-offs represented?...
- Q16. Which of the following is a KEY principle of Business Analysis?...
- Q17. Which of the following statements about prototyping as an investigation technique are FALS...
- Q18. Which elements are included in a CARDI log?