Join the discussion
Question 1/39

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current cost performance index (CPI)?
Correct Answer: A
Add Comments
- Other Question (39q)
- Q1. (Exhibit) The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2...
- Q2. Meetings require:
- Q3. The four steps to writing are:
- Q4. (Exhibit) The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1....
- Q5. A major theme park is expanding the existing facility over a five-year period. The design ...
- Q6. A major theme park is expanding the existing facility over a five-year period. The design ...
- Q7. (Exhibit) The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1...
- Q8. (Exhibit) The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3...
- Q9. A major theme park is expanding the existing facility over a five-year period. The design ...
- Q10. A major theme park is expanding the existing facility over a five-year period. The design ...
- Q11. (Exhibit) The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3...
- Q12. (Exhibit) The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3...
- Q13. _____________is defined as the budget for the cost (work) account times the percent comple...
- Q14. If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Perce...
- Q15. An agricultural corporation that paid 53% in income tax wanted to build a grain elevator d...
- Q16. ____________ is defined as covering work whose component activities are less defined and w...
- Q17. A bond that guarantees the bidder will enter into a contract on the basis of his/her bid i...
- Q18. (Exhibit) The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2...
- Q19. ______________can be defined as the determination of that course of action or combination ...
- Q20. A systematic coding structure for organizing and managing scope, assets, cost, resources, ...
- Q21. An agricultural corporation that paid 53% in income tax wanted to build a grain elevator d...
- Q22. What is a basic element of work or a task that must be performed over a given period of ti...
- Q23. An agricultural corporation that paid 53% in income tax wanted to build a grain elevator d...
- Q24. An agricultural corporation that paid 53% in income tax wanted to build a grain elevator d...
- Q25. An agricultural corporation that paid 53% in income tax wanted to build a grain elevator d...
- Q26. Money is value. Having money when you need it is very important. Money can also be valuabl...
- Q27. (Exhibit) The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1...
- Q28. A major theme park is expanding the existing facility over a five-year period. The design ...
- Q29. (Exhibit) The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2...
- Q30. A major theme park is expanding the existing facility over a five-year period. The design ...
- Q31. (Exhibit) The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1....
- Q32. A major theme park is expanding the existing facility over a five-year period. The design ...
- Q33. An agricultural corporation that paid 53% in income tax wanted to build a grain elevator d...
- Q34. If a project is said to be on a "fast track program/' the fast track method is:...
- Q35. The process of stating goals and determining the most effective way of reaching them is th...
- Q36. In order to withdraw $400 at the end of each year for seven years, what amount should be d...
- Q37. An agricultural corporation that paid 53% in income tax wanted to build a grain elevator d...
- Q38. In a fixed price contract the:
- Q39. An agricultural corporation that paid 53% in income tax wanted to build a grain elevator d...

[×]