Question 113/123
Which of the following levels of the work breakdown structure (WBS) includes an explanation of the purpose of the project?
Correct Answer: A
The correct answer is A. Project . The CSSBB material explains that the work breakdown structure (WBS) expands the project or statement of work into a detailed listing of activities required to complete the work.
This means the highest level of the WBS is the project itself , and that top level carries the overall objective, scope, and purpose. Lower levels such as phases, activities, and tasks are breakdown elements used to organize and execute the work, but they do not define the fundamental purpose of the project.
The CSSBB source also describes a project as a series of activities and tasks with a specified objective , along with starting and ending dates and necessary resources. That objective is what explains the reason or purpose for the effort. Once the project is defined, the WBS decomposes it into smaller pieces for planning and control. Therefore, the explanation of the project's purpose belongs at the project level , not at the phase, activity, or task level. In Six Sigma project management, this top-level definition aligns with the charter and statement of work, making Project the correct answer.
This means the highest level of the WBS is the project itself , and that top level carries the overall objective, scope, and purpose. Lower levels such as phases, activities, and tasks are breakdown elements used to organize and execute the work, but they do not define the fundamental purpose of the project.
The CSSBB source also describes a project as a series of activities and tasks with a specified objective , along with starting and ending dates and necessary resources. That objective is what explains the reason or purpose for the effort. Once the project is defined, the WBS decomposes it into smaller pieces for planning and control. Therefore, the explanation of the project's purpose belongs at the project level , not at the phase, activity, or task level. In Six Sigma project management, this top-level definition aligns with the charter and statement of work, making Project the correct answer.
Add Comments
- Other Question (123q)
- Q1. Which of the following measurement scales classifies data into categories with no implied ...
- Q2. Sally and Sara sell flower pots at their garage sale. Martha motivates Rose mentioning tha...
- Q3. The English words used for the 5S's are Sorting, Straightening, _____________ , __________...
- Q4. The quality leader responsible for the term Total Quality Management (TQM):...
- Q5. A team wants a technique for improving consistency of assembly operations. They should use...
- Q6. Which of the following tools is designed to reduce cycle time?...
- Q7. A team working with a plant relocation is tasked with designing a process for moving 180 p...
- Q8. Find the value of (8) in the ANOVA table. Assume: (Exhibit)...
- Q9. A meeting is called for all three shifts to determine the settings to be used on machine #...
- Q10. Which of the following elements should be included with the documentation for a process fa...
- Q11. When analyzing the behavior of our process to assess customer satisfaction we are concerne...
- Q12. A visual factory has which of the following characteristics?...
- Q13. Approximately what percent of the data values are smaller than the mean?...
- Q14. If an experiment has 5 factors and no replicates for a 2-level Experimental Design with 16...
- Q15. Using the values shown, what is the process yield?...
- Q16. In a failure mode and effects analysis (FMEA), the focus should be on...
- Q17. An automatic gaging system is to be installed in a process. The gage will insert data valu...
- Q18. This QFD matrix was used in the design process for a ball point pen. What symbol is approp...
- Q19. When we compare short-term and long-term Capability which of these is true?...
- Q20. The English words used for the 5S's are Sorting, Straightening, _____________ , __________...
- Q21. Ideally, project team members should be representatives of...
- Q22. A company that is selecting a Six Sigma project from four potential projects should select...
- Q23. The team in the above problem draws arrows from Post-It?notes that are causes to notes tha...
- Q24. The distance between the Mean of a data set and the Point of Inflection on a Normal curve ...
- Q25. Successful Six Sigma projects always:
- Q26. The distribution is:
- Q27. A set of data from a process has 8 readings per sample and 50 samples. The mean of the 50 ...
- Q28. Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for...
- Q29. A set of data from a process has 8 readings per sample and 50 samples. The mean of the 50 ...
- Q30. Which statement(s) are incorrect for the Regression Analysis shown here? (Note: There are ...
- Q31. Which of the following documents is intended to keep an improved process in place, prevent...
- Q32. Find sd:
- Q33. The class score distribution of schools in a metropolitan area is shown here along with an...
- Q34. Which statement(s) are correct about the Regression shown here? (Note: There are 2 correct...
- Q35. Which of the following tools could be used during the optimize phase of a DMADOV project?...
- Q36. A Personal Trainer was assessing her workout class participants for their body fat content...
- Q37. Which statement(s) are correct about the DOE Factorial plot output here? (Note: There are ...
- Q38. A customer focus group is the most effective way for a company to...
- Q39. As a means of measuring the effects on other areas of a process as a result of changes in ...
- Q40. What tool is used to identify relationships that exist between groups of data?...
- Q41. If item A is more likely to be detected than item B which will have the highest Severity v...
- Q42. What dollar amount of savings would a project show if it reduced your outstanding Accounts...
- Q43. Questions that can be best answered by a Visual Factory include all of these except ______...
- Q44. Find sd:
- Q45. Which of the following tools focuses on maximizing equipment effectiveness throughout the ...
- Q46. The _____________ Distribution would be the most desirable for modeling the number of stit...
- Q47. An advantage of using standard deviation rather than range for measuring dispersion of a l...
- Q48. Which of the following techniques will create sample bias?...
- Q49. All the data points that represent the total set of information of interest is called the ...
- Q50. Which of the following actions should be taken during the control phase of a project?...
- Q51. Choose those characteristics of a Simple Linear Regression (SLR) Analysis that are applica...
- Q52. When the Inputs, X's, for your process are Normally Distributed about the Mean, the Output...
- Q53. Which statement(s) are correct about the Factorial Plot shown here? (Note: There are 3 cor...
- Q54. As opposed to earlier emphases lean manufacturing tends to stress:...
- Q55. Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for...
- Q56. Handling of warranty returns, process improvement team meetings and rework to meet custome...
- Q57. Sally and Sara sell flower pots at their garage sale. Sally motivates Sara mentioning that...
- Q58. Approximately what percent of the data values are smaller than the mean?...
- Q59. A dock worker for a feed supplier was tasked with assuring the proper weight in the feed b...
- Q60. The Mann-Whitney test is a powerful test and is unique to situations from which of the cho...
- Q61. To establish a sample size that will allow the proper overlap of distributions we do which...
- Q62. A set of data from a process has 8 readings per sample and 50 samples. The mean of the 50 ...
- Q63. For her injection molding project a Belt needed to track the percentage of defectives of a...
- Q64. A Belt rearranged the location of the parts inventory for a rework station locating the mo...
- Q65. There have been some instances in which 1.5 inch sheet metal screws are used where 1.25 in...
- Q66. Which of these might contribute to similar distributions having Unequal Variance?...
- Q67. There are 14 different defects that can occur on a completed time card. The payroll depart...
- Q68. This table displays the inventory of fasteners in a storage cabinet. A bolt is selected at...
- Q69. A complex system has many causes and effects. These may be illustrated on which of the fol...
- Q70. When a Black Belt is running a designed experiment, which of the following details can be ...
- Q71. A Belt working in a supply chain environment has to make a decision to change suppliers of...
- Q72. A team working with a plant relocation is tasked with designing a process for moving 180 p...
- Q73. Here is a partial ANOVA table. Use = 0.05. (Exhibit) The values of x, y and z should be:...
- Q74. If you can Poka-Yoke a defect out of the process entirely then you do not need use SPC on ...
- Q75. Using standard work will help increase
- Q76. The calculation of Column Total times Row Total divided by Grand Total yields expected val...
- Q77. A statistical test or Hypothesis Test is performed to reject or fail to reject a stated hy...
- Q78. A population of size 1,000,000 has mean 42 and standard deviation 6. Sixty random samples,...
- Q79. Which of these items contribute to what is necessary for successful Kaizen events?...
- Q80. A natural logarithmic base is not required for which of these distributions for probabilit...
- Q81. A process improvement team will be most effective if it includes which of the following ty...
- Q82. A Belt has determined that the inventory of repair parts at a rework station can be reduce...
- Q83. Which Element of Waste best describes "the unnecessary movement of materials and goods"?...
- Q84. The following control chart was developed by a continuous improvement team. (Exhibit) The ...
- Q85. A team wants a technique for determining and displaying priorities based on frequency of v...
- Q86. The reported Cpk for a process with an average of 104 units, a spread of 18 units and uppe...
- Q87. Find the value of (9) in the ANOVA table. Assume: (Exhibit)...
- Q88. What conclusion is most correct about the Experimental Design shown here with the response...
- Q89. The financial perspective of a balanced scorecard provides stakeholders with an...
- Q90. A team has been asked to reduce the cycle time for a process. The team decides to collect ...
- Q91. Which statement(s) are correct about the DOE Factorial plot output here? (Note: There are ...
- Q92. As DMAIC projects are rolled out to process owners and staff, training needs to focus on...
- Q93. The distribution of sample means will approach a normal distribution whenever the...
- Q94. Find Cp
- Q95. A Black Belt is managing a team that encounters an organizational problem caused by confli...
- Q96. Company ABC provides components directly to Company XYZ, which incorporates them into its ...
- Q97. A principle disadvantage of fractional factorial experimental designs is:...
- Q98. A Belt working in a supply chain environment has to make a decision to change suppliers of...
- Q99. A complex system has many causes and effects. These may be illustrated on which of the fol...
- Q100. The preferred method for determining statistically whether factor A or B is significant re...
- Q101. Using this partial Z Table, how many units from a month's production run are expected to n...
- Q102. Find the value of (11) in the ANOVA table. Assume: (Exhibit)...
- Q103. Customers make their decisions based on Features, Integrity (of the seller) Delivery and _...
- Q104. A process has a specification of 5.2 ± 0.3 and yields the following data: What is the Ppk ...
- Q105. A team has calculated the following invoice processing time for accounting personnel. What...
- Q106. A Lean Six Sigma project is attempting to reduce inventory days. The Process Capability wi...
- Q107. If the probability that event A occurs is 0.51, the probability that event B occurs is 0.6...
- Q108. A set of data from a process has 8 readings per sample and 50 samples. The mean of the 50 ...
- Q109. A normal population has a known variance of 5.9 mm². What sample size would be required to...
- Q110. Proposed Six Sigma projects that are not in some way linked to organizational goals:...
- Q111. A project whose definition does not include performance metrics:...
- Q112. If a Six Sigma project was to reduce changeover times and the team found the project succe...
- Q113. Which of the following levels of the work breakdown structure (WBS) includes an explanatio...
- Q114. When we gather information for the Voice of the Business we are primarily interested in in...
- Q115. The average number of defects is 21.6. Find the upper control limit for the c-chart....
- Q116. A Belt is analyzing data and upon creation of the graphical analysis sees multiple modes. ...
- Q117. A fundamental rule is that both Standard Deviation and Variance can be added....
- Q118. Special Cause Variation falls into which two categories?...
- Q119. A team's goal is to improve information flow in a payroll function. They make thirty-three...
- Q120. Which of the following roles is responsible for reviewing and approving any changes to a S...
- Q121. The most appropriate type of FMEA for a product before going into manufacturing is a _____...
- Q122. Which of these are examples of business metrics or Key Performance Indicators commonly ref...
- Q123. A Factorial Experiment based on a Level 2 Design with 6 factors would require 16 runs to f...