A client wants to remove the gypsum board from an existing structural column and leave it exposed. What implications might this have on the fire rating of the assembly?
Correct Answer: A
Gypsum board on a structural column (e.g., steel) provides fire resistance by insulating the structural member, per IBC Chapter 7. Removing it exposes the column, reducing its fire rating (e.g., from 2-hour to unprotected), as steel loses strength in heat without protection. Increasing (B) is impossible without adding fireproofing. No change (C) ignores gypsum's protective role.Reduction (A) reflects the loss of fire resistance.
Verified Answer from Official Source:A - Reduce the fire rating of the assembly
"Removing gypsum board from a structural column reduces the fire rating by eliminating its protective layer, per IBC requirements." (NCIDQ IDPX Study Guide, Section 1: Codes and Standards) Explanation from Official Source:The NCIDQ aligns with IBC, noting that fire-rated assemblies rely on finishes like gypsum for protection, critical for structural safety.
Objectives:
* Apply fire protection codes (IDPX Objective 1.4).
Verified Answer from Official Source:A - Reduce the fire rating of the assembly
"Removing gypsum board from a structural column reduces the fire rating by eliminating its protective layer, per IBC requirements." (NCIDQ IDPX Study Guide, Section 1: Codes and Standards) Explanation from Official Source:The NCIDQ aligns with IBC, noting that fire-rated assemblies rely on finishes like gypsum for protection, critical for structural safety.
Objectives:
* Apply fire protection codes (IDPX Objective 1.4).
Add Comments
- Other Question (83q)
- Q1. A client wants to remove the gypsum board from an existing structural column and leave it ...
- Q2. In a large project, what is the BEST reason to enter into a joint venture?...
- Q3. The ground floor of a building contains a mixed occupancy with a retail store (9,500 sf [8...
- Q4. Which of the following is MOST likely to require a louvered door?...
- Q5. The interior designer presents budget options based on quality ranges and the client appro...
- Q6. Which space would MOST likely have a dedicated HVAC system?...
- Q7. What should a designer recommend to BEST save on construction costs in a corporate office ...
- Q8. Information regarding product substitutions is found in the...
- Q9. When does a project team gather information about a company's culture, mission, values, an...
- Q10. Which characteristic of a water closet is MOST likely to impact the partition layout?...
- Q11. A building code official has declined to issue a building permit for a project. The offici...
- Q12. When estimating the total FF&E costs for installation, maintenance, and replacement, w...
- Q13. Gross leasable area is measured from the
- Q14. Which drawings and information would be presented during the design development phase?...
- Q15. Referencing the table below, which two spaces could be combined as part of the space needs...
- Q16. The project team is reviewing a mock-up of a faux plaster ceiling finish. The mock-up is a...
- Q17. With regard to electrical systems, one responsibility of an interior designer is to provid...
- Q18. A corporate client tells their designer that they will be purchasing all of their ancillar...
- Q19. What is the standard sequence of events for the permit process?...
- Q20. A new hospital includes a cafeteria and a 60-person conference room. Which occupancy class...
- Q21. A storage area has been approved as an accessory occupancy within a retail store. The mean...
- Q22. What is the MINIMUM aisle width in retail areas conforming to universal accessibility stan...
- Q23. A contractor defaults on payments to a mechanical subcontractor. The subcontractor is prot...
- Q24. The specification of which item is within the scope of work for interior designers when de...
- Q25. Which of the following would allow for ease of reconfiguration of power and data for open ...
- Q26. While performing a survey of an existing elevator lobby in a sprinklered commercial buildi...
- Q27. A lien has been placed on a building. What may be a probable cause for this action?...
- Q28. When reviewing the general contractor's pay application, the designer should approve the a...
- Q29. During an office renovation, a financial firm wants to continue occupying the space while ...
- Q30. A residential client wants to build an addition that would occupy the entire side-yard. Wh...
- Q31. During construction of a project in another city, what is a common and efficient way for a...
- Q32. An interior designer was contacted by their client shortly after occupancy and move-in, co...
- Q33. What is the MOST critical aspect of an existing building to check before locating library ...
- Q34. What modification would increase the available time for occupants to exit a space during a...
- Q35. In addition to the use of carpet on the floor, which of the following methods is the BEST ...
- Q36. What is the term for a full-scale representation of products or construction features that...
- Q37. A building owner hires a design firm to renovate an existing office suite into a live-work...
- Q38. A designer is working on a joint venture project with a local engineering firm for a large...
- Q39. A restaurant is designated as which occupancy classification?...
- Q40. The office manager for a client signed a contract for design services. However, the owner ...
- Q41. Which of the following installations would require a structural engineer to be involved?...
- Q42. Which scheduling method BEST shows the interrelationships of tasks?...
- Q43. What is the MINIMUM distance a vending machine can be located on the push side of a door w...
- Q44. Who conducts post-occupancy evaluation interviews?...
- Q45. What are the PRIMARY components of sustainability?...
- Q46. The role of the project manager includes
- Q47. While on site, the designer notices that the glazing subcontractor is installing the store...
- Q48. Plumbing traps are an essential feature of sanitary drains because they prevent...
- Q49. Delivery of product directly to the client's address is known as...
- Q50. What method of payment for interior design services poses the least financial risk to the ...
- Q51. What spaces are typically grouped together in a multistory building's service core?...
- Q52. What core information should be captured in the design contract to demonstrate a clear und...
- Q53. The PRIMARY reason for the submittal process during Contract Administration is for the des...
- Q54. A mock-up is provided after client review of the finishes and systems furniture components...
- Q55. A conflict on the job site impacts the location of a wall sconce, requiring an adjustment....
- Q56. What is the MINIMUM fire rating for a door in a 2-hour fire separation wall?...
- Q57. What provision should a designer include in the contract to minimize liability in claims t...
- Q58. What is the PRIMARY benefit for incorporating a design firm?...
- Q59. What is the MOST effective construction method to help mitigate impact noise from high hee...
- Q60. A post-occupancy evaluation indicates that occupants are cold during winter months due to ...
- Q61. A designer is hired to update a community clubhouse in a private residential subdivision. ...
- Q62. Which consultant should be contacted to correct omissions on the drawing shown below? (Exh...
- Q63. A designer has a contract with a client to provide complete contract documents for a tenan...
- Q64. When special equipment is being leased by a tenant from a third-party vendor, who is typic...
- Q65. What is the term for a continuous path of travel from any point in a building or structure...
- Q66. Changes made to the contract documents during the bid (tender) process are documented in a...
- Q67. Which wall section provides for a two-hour fire-rated wall? (Exhibit)...
- Q68. What floor finish would BEST support a passive solar design strategy in a hot arid climate...
- Q69. What is the MAXIMUM occupant load of a business occupancy with one exit?...
- Q70. What do written specifications define?
- Q71. After completion of a project, the client spills coffee on their new lobby sofa. Where wou...
- Q72. What is the allowable reach range for an obstructed side reach over a kitchen counter?...
- Q73. Which person is MOST responsible for ensuring that the construction drawings are code-comp...
- Q74. Which specification will offer interior designers the most control of the furniture system...
- Q75. In a project that includes a home renovation and procurement of new furniture, what is the...
- Q76. What is required prior to occupancy to improve indoor air quality?...
- Q77. In which type of space would occupant load be calculated using net square footage?...
- Q78. While visiting a job site, it is observed that the junction boxes for wall sconces are mou...
- Q79. Any space that is classified as an assembly occupancy MUST have...
- Q80. The client has approved a selection for lounge seating and has selected a COM fabric for i...
- Q81. If the net square footage [m²] is 50,000 square feet [4,645 m²] and usable square footage ...
- Q82. The designer attends the weekly progress meetings and is responsible for the meeting minut...
- Q83. What would be included as part of a fire separation (fire assembly)?...