Join the discussion
Question 1/21
You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.

Given this information what should you conclude?

Given this information what should you conclude?
Correct Answer: B
* Cost of Quality Analysis:
* The given table lists costs for defect prevention, appraisal, internal failure, and external failure.
* Defect prevention cost is $50,000, while costs for appraisal, internal failures, and external failures are $250,000, $200,000, and $200,000, respectively.
* The combined cost of internal and external failures is significantly high compared to defect prevention costs.
* Defect Detection and Prevention (DDP):
* DDP measures the effectiveness of defect prevention activities and early detection mechanisms.
* In this case, 1,000 defects were caught before release (appraisal) and 100 defects escaped to production.
* DDP = (Defects found before release / Total defects) = 1000 / (1000 + 100) = 90.91%.
* While this DDP is relatively high, the costs of appraisal and failures indicate that prevention strategies need more investment.
* Key Cost Drivers:
* High internal and external failure costs indicate inefficiencies in earlier stages of quality assurance.
* Shifting investments from appraisal and failure costs towards defect prevention would reduce the overall cost of quality.
* Evaluating Options:
* Option A ("More testing needed because DDP < 90%") is invalid since DDP is above 90%.
* Option C ("The cost of testing is justified") does not address the imbalance between high failure costs and low prevention spending.
* Option D ("More effort on appraisal") contradicts the cost-benefit focus of investing in prevention.
* Option B is correct because enhancing defect prevention strategies will reduce downstream costs.
References and Syllabus Alignment:
* This conclusion aligns with the ISTQB Advanced Test Management syllabus section on "Cost of Quality" and strategies to optimize testing investments. Specifically, prevention is emphasized as more cost-effective than appraisal and failure management.
* The given table lists costs for defect prevention, appraisal, internal failure, and external failure.
* Defect prevention cost is $50,000, while costs for appraisal, internal failures, and external failures are $250,000, $200,000, and $200,000, respectively.
* The combined cost of internal and external failures is significantly high compared to defect prevention costs.
* Defect Detection and Prevention (DDP):
* DDP measures the effectiveness of defect prevention activities and early detection mechanisms.
* In this case, 1,000 defects were caught before release (appraisal) and 100 defects escaped to production.
* DDP = (Defects found before release / Total defects) = 1000 / (1000 + 100) = 90.91%.
* While this DDP is relatively high, the costs of appraisal and failures indicate that prevention strategies need more investment.
* Key Cost Drivers:
* High internal and external failure costs indicate inefficiencies in earlier stages of quality assurance.
* Shifting investments from appraisal and failure costs towards defect prevention would reduce the overall cost of quality.
* Evaluating Options:
* Option A ("More testing needed because DDP < 90%") is invalid since DDP is above 90%.
* Option C ("The cost of testing is justified") does not address the imbalance between high failure costs and low prevention spending.
* Option D ("More effort on appraisal") contradicts the cost-benefit focus of investing in prevention.
* Option B is correct because enhancing defect prevention strategies will reduce downstream costs.
References and Syllabus Alignment:
* This conclusion aligns with the ISTQB Advanced Test Management syllabus section on "Cost of Quality" and strategies to optimize testing investments. Specifically, prevention is emphasized as more cost-effective than appraisal and failure management.
Add Comments
- Other Question (21q)
- Q1. You have assembled the following cost of quality numbers 1 000 defects were found prior to...
- Q2. You have been asked to make a recommendation on deployment readiness on the software your ...
- Q3. You have been assigned to a project that has a very tight schedule.In fact, given your fir...
- Q4. You are a new lest manager in an organization You have been asked to assess the defect pro...
- Q5. Which test process improvement model consists of five maturity levels?...
- Q6. You areworking In an environment that is continually pushing process improvements down to ...
- Q7. You are managing the test team that is testing a new mobile application that provides a "s...
- Q8. Youare working with a development team who have a CI/CD pipeline implemented.They want to ...
- Q9. You have been asked to estimate the testing effort for an upgrade to a legacy product Your...
- Q10. You have assembled the following cost of quality numbers 200 defects were found prior to r...
- Q11. Your team has been working on anAgile project for two months.There is a retrospective at t...
- Q12. You are looking to Improve the efficiency of testing. The developers have been claiming th...
- Q13. Which ofthe following Is the common setof information to be produced in a test estimate''...
- Q14. Which of the following is the proper order for the stages of a toollifecycle?...
- Q15. In what environment are you mostlikely to see multiple defect management systems used in o...
- Q16. You are working for an outsource testing company You have a client that will only consider...
- Q17. You have been seeing a high number of rejections of defect reports The developers are comp...
- Q18. Which of the Mowing Is commonly used by a test manager to identity risks'...
- Q19. Your defect opened trend is converging to the closed trend but there is still a gap. What ...
- Q20. Your team has been working on anAgile project for two months.There is a retrospective at t...
- Q21. If you are monitoring code coverage during testing to determine what areas still need test...
