Join the discussion
Question 268/621
What is the difference between verified and accepted deliverables?
Correct Answer: C
Add Comments
- Other Question (621q)
- Q1. In which Project Cost Management process is work performance data included?...
- Q2. During the execution phase of a multibillion-dollar project, the project manager encounter...
- Q3. A project's purpose or justification, measurable project objectives and related success cr...
- Q4. During what project management process does the project manager invest the most effort int...
- Q5. A project manager submitted a project proposal to a client. A few days later, the client s...
- Q6. Which of the following Project Communication Management processes uses performance reports...
- Q7. The process of establishing the policies, procedures, and documentation for planning, deve...
- Q8. Which item is an output of Plan Quality Management and an input to Perform Quality Assuran...
- Q9. The project manager is working in the Resource Management process. Which items may the pro...
- Q10. The number of potential communication channels for a project with 5 stakeholders is:...
- Q11. Which type of diagram includes groups of information and shows relationships between facto...
- Q12. Which type of diagram includes groups of information and shows relationships between facto...
- Q13. What is the probability of occurrence if the risk rating is 0.56 and the impact if the ris...
- Q14. Which action should a project manager take to ensure that the project management plan is e...
- Q15. When a project is undertaken to reduce defects in a product or service, the objective of t...
- Q16. At which point of the project is the uncertainty the highest and the risk of failing the g...
- Q17. The process of identifying specific actions to be performed to produce project deliverable...
- Q18. The project manager and the project team are in the process of documenting procurement dec...
- Q19. Which of the following factors within a company cloud trigger the creation of a project?...
- Q20. A project manager has a project schedule baseline. How can the critical path be determined...
- Q21. Which of the following is a tool and technique used to monitor risk?...
- Q22. An input required in Define Scope is an organizational:...
- Q23. A project manager read the initial contract when a project was started. The contract state...
- Q24. A project manager is reviewing some techniques that can be used to evaluate solution resul...
- Q25. Which sentence summarizes the salience model?
- Q26. Which of the following is an example of tacit knowledge?...
- Q27. Which illustrates the connection between work that needs to be done and its project team m...
- Q28. When executing a project, a recently hired subject matter expert (SME) who reviewed the ex...
- Q29. Stakeholder identification and engagement should begin during what phase of the project?...
- Q30. Which is the order of steps in the Procurement Management process?...
- Q31. Which type of graphic is displayed below? (Exhibit)...
- Q32. Which group is formally chartered and responsible for reviewing, evaluating, approving, de...
- Q33. Correlated and contextualized information on how closely the scope is being maintained rel...
- Q34. A practitioner organized a requirements workshop with the client ' s frontline application...
- Q35. What is the most important skill that project managers should possess to lead stakeholders...
- Q36. The Plan Stakeholder Management process belongs to which Process Group?...
- Q37. Which of the following is an external enterprise environmental factor (EEF) in a business ...
- Q38. What are the identified risks for doing excessive decomposition in a WBS?...
- Q39. Expected monetary value (EMV) is computed by which equation?...
- Q40. During which process does the project team receive bids and proposals?...
- Q41. What important leadership quality/qualities should project managers possess?...
- Q42. Which tool or technique is used in the Plan Scope Management process?...
- Q43. Which Process Group typically consumes the bulk of a project's budget?...
- Q44. Which is an output of the Collect Requirements process?...
- Q45. Which components of the project management plan are inputs used when creating the stakehol...
- Q46. A project manager uses their networking skills to build agreement with a difficult stakeho...
- Q47. An output of the Plan Quality Management process is:...
- Q48. Calculate the Schedule Performance Index (SPI) based on the following information: earned ...
- Q49. An organizational structure that standardizes the project-related governance and facilitat...
- Q50. In a project using agile methodology, who may perform the quality control activities?...
- Q51. An input required in Define Scope is an organizational:...
- Q52. An effective technique for resolving conflict that incorporates multiple viewpoints from d...
- Q53. Which of the following response strategies are appropriate for negative risks or threats?...
- Q54. The procurement process that documents agreements and related documentation for future ref...
- Q55. What is the responsibility of the project manager and the functional manager respectively?...
- Q56. A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique...
- Q57. Considering a highly dynamic project environment, which approach should the project manage...
- Q58. Which of the following are outputs of the Define Scope process in Project Scope Management...
- Q59. Which tool or technique is an examination of industry and specific vendor capabilities?...
- Q60. Which of the following can a project manager conduct if they have a stakeholder who is unr...
- Q61. A stakeholder expresses a need not known to the project manager. The project manager most ...
- Q62. Which of the following factors is lowest at the start of the project?...
- Q63. What does a sender-receiver model accomplish?
- Q64. A project manager is updating their CV or resume and realizes that they need to improve sk...
- Q65. Stakeholder satisfaction should be managed as a key project:...
- Q66. Which Process Group contains the processes performed to complete the work defined in the p...
- Q67. Which of the following is an output from Control Scope?...
- Q68. Which of the following is a statistical concept that calculates the average outcome when t...
- Q69. In what type of organizational structure does a project manager develop their role and wor...
- Q70. Match each Project Cost Management process with its appropriate keyword (Exhibit)...
- Q71. Which characteristics do effective project managers possess?...
- Q72. Which process involves defining, preparing, and coordinating all subsidiary plans and inte...
- Q73. A tool and technique used during the Perform Qualitative Risk Analysis process is:...
- Q74. For what project management process is work performance information an output?...
- Q75. Which task will a project manager undertake while conducting Project Resource Management?...
- Q76. What is the purpose of an adaptive standup meeting?...
- Q77. Completion of the product scope is measured against the product:...
- Q78. The project manager needs to manage a critical issue immediately, and this requires action...
- Q79. In an adaptive or agile life cycle, how are the customer and sponsor involved in the proje...
- Q80. Which of the following documents are created as part of Project Integration Management?...
- Q81. The risk shared between the buyer and seller is determined by the:...
- Q82. Organizational planning impacts projects by means of project prioritization based on risk,...
- Q83. What is a deliverable-oriented, hierarchical decomposition of the work to be executed to a...
- Q84. Directing another person to get from one point to another using a known set of expected be...
- Q85. The following is a network diagram for a project. (Exhibit) The free float for Activity E ...
- Q86. Which of the following is used to classify stakeholders based on their assessments of powe...
- Q87. The project manager notes that stakeholders are aware of the project and potential impacts...
- Q88. Project contracts generally fall into which of the following three broad categories?...
- Q89. Why is tailoring in a project necessary?
- Q90. A project team attempts to produce a deliverable and finds that they have neither the expe...
- Q91. Activity cost estimates and the project schedule are inputs to which Project Cost Manageme...
- Q92. An output of the Direct and Manage Project Work process is:...
- Q93. The project manager needs to manage a critical issue immediately, and this requires action...
- Q94. A practitioner organized a requirements workshop with the client ' s frontline application...
- Q95. The primary benefit of the Plan Schedule Management process is that it:...
- Q96. If you are using an Ishikawa diagram to determine the root cause of problems, which proces...
- Q97. Which tools and techniques should a project manager use when estimating costs?...
- Q98. Which type of managers do composite organizations involve?...
- Q99. Which set of activities should a project manager use as part of the Develop Team process?...
- Q100. Which type of dependency is established based on knowledge of best practices within a part...
- Q101. The Define Scope process is in which of the following Process Groups?...
- Q102. Funding limit reconciliation is a tool and technique of which Project Cost Management proc...
- Q103. Which input provides suppliers with a clear set of goals, requirements, and outcomes?...
- Q104. What does expert judgment provide as an input to the resource management plan?...
- Q105. Which of the seven basic quality tools is especially useful for gathering attributes data ...
- Q106. Every project creates a unique product, service, or result that may be:...
- Q107. An organization is establishing a project management office (PMO). A senior manager from o...
- Q108. What is Project Portfolio Management?
- Q109. Which of the following reduces the probability of potential consequences of project risk e...
- Q110. Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?...
- Q111. Which type of project management office (PMO) supplies templates, best practices, and trai...
- Q112. An international company that is starting to practice an adaptive approach has several dev...
- Q113. The process of identifying and documenting relationships among the project activities is k...
- Q114. A tool and technique used during the Collect Requirements process is:...
- Q115. A construction project is underway, and during... tasks impacted the painting work A const...
- Q116. Which of the following is the key construction to controlling the costs and achieving the ...
- Q117. A project manager has reached an agreement on the requirements and now needs to define the...
- Q118. The following is a network diagram for a project. (Exhibit) How many possible paths are id...
- Q119. What communication methods would a project manager use for overall effective project commu...
- Q120. Which of the following is a strategy to deal with positive risks or opportunities?...
- Q121. An electronics firm authorizes a new project to develop a faster, cheaper, and smaller lap...
- Q122. As the project progresses, which of the following is routinely collected from the project ...
- Q123. A project manager is responsible for delivering new software for their company. Based on p...
- Q124. An input to the Collect Requirements process is the:...
- Q125. Which three processes are generally included in risk management? (Choose three.)...
- Q126. Which output of Project Cost Management consists of quantitative assessments of the probab...
- Q127. Which is an example of Administer Procurements?...
- Q128. Within project integration management, the statement of work (SOW) references which aspect...
- Q129. Grouping the stakeholders based on their level of authority and their level of concern reg...
- Q130. Perform Integrated Change Control is the process of:...
- Q131. What does earned value (EV) measure?
- Q132. Which of the following is an output of the Plan Quality process?...
- Q133. A disadvantage associated with virtual teams is that they:...
- Q134. What is the role of project management in terms of organizational strategy?...
- Q135. Which task will a project manager undertake while conducting Project Resource Management?...
- Q136. The features and functions that characterize a result, product, or service can refer to:...
- Q137. While processes in the Planning Process Group seek to collect feedback and define project ...
- Q138. Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted...
- Q139. Which Process Group contains the processes performed to complete the work defined in the p...
- Q140. The project manager is using co-location and providing training to the project team. On wh...
- Q141. Which document in the project management plan can be updated in the Plan Procurement Manag...
- Q142. The ways in which the roles and responsibilities, reporting relationships, and staffing ma...
- Q143. A project manager needs to demonstrate that the project meets quality standards and succes...
- Q144. A car company authorized a project to build more fuel-efficient cars in response to gasoli...
- Q145. Which enterprise environmental factors may influence Plan Schedule Management?...
- Q146. According to PMBOK, the definition of Plan Risk Management is:...
- Q147. Which of the following conditions should the project manager consider when working on the ...
- Q148. A project manager has reached an agreement on the requirements and now needs to define the...
- Q149. One of the objectives of a quality audit is to:...
- Q150. A project team for a marketing company is acquiring leaflets and materials from competitor...
- Q151. The project manager and the project team are having a meeting with the purpose of identify...
- Q152. Which type of management focuses on ensuring that projects and programs are reviewed to pr...
- Q153. Which process is included in the Project Integration Management Knowledge Area?...
- Q154. Which enterprise environmental factors may influence Plan Schedule Management?...
- Q155. A construction project is underway, and during the progress review the painter complained ...
- Q156. A product owner wants to ensure that the project ' s requirements, including product requi...
- Q157. In which phase of team building activities do team members begin to work together and adju...
- Q158. Organizational process assets, a lessons-learned database, and historical information are ...
- Q159. The project manager released a report. A few stakeholders express the view that the report...
- Q160. Within a matrix organization, dual reporting of team members is a risk for project success...
- Q161. A measure of cost performance that is required to be achieved with the remaining resources...
- Q162. Which of the following is an example of an organizational system that is arranged based on...
- Q163. In addition to the project charter, what other artifact is produced as a result of the Dev...
- Q164. Which Knowledge Area is concerned with the processes required to ensure timely and appropr...
- Q165. What is the project manager's responsibility in Project Integration Management?...
- Q166. Labor, materials, equipment, and supplies are examples of:...
- Q167. Risk categorization is a tool or technique used in which process?...
- Q168. An input to Develop Project Charter is a/an:
- Q169. What method for categorizing stakeholders is suitable for small projects with simple relat...
- Q170. Which tool or technique is used in the Perform Integrated Change Control process?...
- Q171. A project team member agrees to change a project deliverable after a conversation with an ...
- Q172. When does Monitor and Control Risks occur?
- Q173. Definitions of probability and impact, revised stakeholder tolerances, and tracking are co...
- Q174. Sharing good practices introduced or implemented in similar projects in the organization a...
- Q175. Sending letters, memos, reports, emails, and faxes to share information is an example of w...
- Q176. Which are the most important competencies required for a project manager?...
- Q177. Which group creativity technique asks a selected group of experts to answer questionnaires...
- Q178. Which type of dependency used in the Sequence Activities process is sometimes referred to ...
- Q179. Which Define Activities output extends the description of the activity by identifying the ...
- Q180. Which tool or technique is effective in a project in which the deliverable is not a servic...
- Q181. The diagram below is an example of a: (Exhibit)...
- Q182. The completion of the project scope is measured against the:...
- Q183. A project manager is considering whether or not to procure a new vendor. What can the proj...
- Q184. Which process uses expert judgment to manage project resources?...
- Q185. The project manager is creating the communications management plan. Which group of inputs ...
- Q186. During what project management process does the project team begin identifying risks?...
- Q187. Using parametric estimating, if an assigned resource is capable of producing 120 units per...
- Q188. A project manager is reviewing some techniques that can be used to evaluate solution resul...
- Q189. Project managers who lead by example and follow through on the commitments they make demon...
- Q190. The project management processes are usually presented as discrete processes with defined ...
- Q191. A project team is closing out a phase and updating the organizational knowledge base What ...
- Q192. A project manager is working in an environment where requirements are not very clear and m...
- Q193. Which of the following project documents is an input to the Control Scope process?...
- Q194. Which type of estimating can produce higher levels of accuracy, depending upon the sophist...
- Q195. A technical project manager uses a directive approach with the team. Some team members are...
- Q196. In which process might a project manager use risk reassessment as a tool and technique?...
- Q197. Deciding the phases of a project life cycle would be considered a part of which of these k...
- Q198. Which quality tool incorporates the upper and lower specification limits allowed within an...
- Q199. Which components of the project can be updated as a result of managing stakeholder engagem...
- Q200. Which of the following terms indicates a deliverable-oriented hierarchical decomposition o...
- Q201. Sharing good practices introduced or implemented in similar projects in the organization a...
- Q202. Which Project Management Process Group includes Collect Requirements, Define Activities, S...
- Q203. The project manager and the project team are having a meeting with the purpose of identify...
- Q204. Which stakeholder communicates with higher levels of management to gather organizational s...
- Q205. The most appropriate project life cycle model for an environment with a high level of chan...
- Q206. Which schedule network analysis technique modifies the project schedule to account for lim...
- Q207. Which type of organizational structure is displayed in the diagram provided? (Exhibit)...
- Q208. In project management, a temporary project can be:...
- Q209. Cost baseline is an output of which of the following processes?...
- Q210. Which three techniques can be estimate costs?
- Q211. Which characteristic defines the Delphi technique of group decision-making?...
- Q212. The cost performance baseline is typically displayed in the form of:...
- Q213. An output of the Validate Scope process is:
- Q214. What characteristic of servant leadership supports resource management in an agile environ...
- Q215. An executive sponsor wants to be briefed on how the product will change over time. Which d...
- Q216. A project sponsor has asked the project manager to determine how soon the project can be c...
- Q217. The diagram below is an example of a:
- Q218. The methodology that combines scope, schedule, and resource measurements to assess project...
- Q219. Which of the following terms indicates a deliverable-oriented hierarchical decomposition o...
- Q220. An output of the Perform Integrated Change Control process is:...
- Q221. A business analyst wants to know who to contact about a roadblock on a specific feature. W...
- Q222. The precedence diagramming method (PDM) is also known as:...
- Q223. What tools or techniques can be used in all cost management processes'?...
- Q224. Which is one of the determining factors used to calculate CPI?...
- Q225. Which of the following is an information gathering technique in Identify Risks?...
- Q226. Which tool and technique is used in Conduct Procurements?...
- Q227. After an internal deliverable review session with the team, the project manager indicates ...
- Q228. Plan Risk Management is the process of defining how to:...
- Q229. A construction project is underway, and during... tasks impacted the painting work A const...
- Q230. Which Plan Schedule Management tool or technique may involve choosing strategic options to...
- Q231. During which process of Project Cost Management does a project manager produce the cost ba...
- Q232. Which type of risk diagram is useful for showing time ordering of events?...
- Q233. Which Subsidiary management plan would a project manager create to manage Information diss...
- Q234. Which statement summarizes the role of the change control board?...
- Q235. What is one of the main purposes of the project charter?...
- Q236. A business case is being assembled. Which two elements are necessary to complete this proc...
- Q237. What describes the relationship between projects, programs, and portfolios?...
- Q238. A few project team members are having issues understanding the requirements as described. ...
- Q239. Which quality tool incorporates the upper and lower specification limits allowed within an...
- Q240. The cost performance baseline is typically displayed in the form of:...
- Q241. The Verify Scope process is primarily concerned with:...
- Q242. Which of the following statements correctly characterizes pull communication?...
- Q243. If the most likely duration of an activity is five weeks, the best-case duration is two we...
- Q244. A project manager is reviewing the change requests, deliverables, and the project plan in ...
- Q245. Configuration identification, configuration status accounting, and configuration verificat...
- Q246. Managing ongoing production of goods and services to ensure business continues efficiently...
- Q247. Who identifies project requirements in the early phase of the project?...
- Q248. A project manager has just consolidated the project risk management plan and sent it to th...
- Q249. For a stakeholder with low interest and high power, the project manager should:...
- Q250. Which of the following is developed from the project scope baseline and defines only that ...
- Q251. Changes to formally controlled documentation, plans, etc. to reflect modified or additiona...
- Q252. Who is responsible for initiating a project?
- Q253. A project manager has a project schedule baseline. How can the critical path be determined...
- Q254. Which process involves determining, documenting, and managing stakeholders' needs and requ...
- Q255. In the last two iterations, a project team failed to deliver all of the stories on time. W...
- Q256. Company A has just been notified about a new legal requirement for its business operations...
- Q257. Plan Communications Management develops an approach and plan for project communications ba...
- Q258. What process is performed periodically throughout the project as needed?...
- Q259. The table represents the possible durations of a specific project task. (Exhibit) Using th...
- Q260. Which of the following tools and techniques is used in the Develop Project Team process?...
- Q261. The primary benefit of the Plan Schedule Management process is that it:...
- Q262. What is the best tool to calculate the critical path on a project?...
- Q263. An element of the modern quality management approach used to achieve compatibility with th...
- Q264. The following is a network diagram for a project. (Exhibit) What is the critical path for ...
- Q265. Which basic quality tool is most useful when gathering attributes data in an inspection to...
- Q266. In which process is a project manager identified and given the authority to apply resource...
- Q267. Taking out insurance in relation to risk management is called what?...
- Q268. What is the difference between verified and accepted deliverables?...
- Q269. A collection of projects managed as a group to achieve strategic objectives is referred to...
- Q270. What is the role of project management in terms of organizational strategy?...
- Q271. Which of the following are outputs from the process of creating a work breakdown structure...
- Q272. (Exhibit) As the project takes place and some issues arose, the project manager (Joe) find...
- Q273. In a construction project schedule, what is the logical relationship between the delivery ...
- Q274. Why is tailoring in a project necessary?
- Q275. What tool should a project manager use to efficiently manage project resources?...
- Q276. Which statement describes the relationship between Manage Quality process and Control proc...
- Q277. A project manager has the task of determining the deliverables for a six-month project usi...
- Q278. The process of identifying and documenting the specific actions to be performed to produce...
- Q279. What is the most important skill that project managers should possess to lead stakeholders...
- Q280. An input to the Create WBS process is a:
- Q281. How many Project Management Process Groups are there?...
- Q282. Which quality control technique illustrates the 80/20 principle?...
- Q283. The completion of the project scope is measured against the:...
- Q284. Which type of project life cycle uses an iteration plan?...
- Q285. Quality metrics are an output of which process?...
- Q286. A team has been tasked with designing a product to address a problem they have never faced...
- Q287. Which conflict resolution technique produces the most lasting results?...
- Q288. A recently hired project manager is looking for templates to use for projects on which the...
- Q289. What scope definition technique is used to generate different approaches to execute and pe...
- Q290. The following chart contains information about the tasks in a project. (Exhibit) Based on ...
- Q291. Which action should the project manager take after the team finishes executing the scope?...
- Q292. Which term describes an assessment of correctness?...
- Q293. What is the responsibility of the project manager and the functional manager respectively?...
- Q294. When large or complex projects are separated into distinct phases or subprojects, all of t...
- Q295. A project manager has created an issue log to document issues communicated by project team...
- Q296. Which of the following is an example of an internal factor that influences the outcome of ...
- Q297. A risk that arises as a direct result of implementing a risk response is called a:...
- Q298. What are the project management processes associated with project quality management?...
- Q299. Which term describes an assessment of correctness?...
- Q300. A company has implemented an adaptive project management framework for a new project. When...
- Q301. The definition of operations is a/an:
- Q302. A software team has completed a critical feature and demonstrated it to the project sponso...
- Q303. At what stages of project should the identify Stakeholder process be performed?...
- Q304. In which sphere of influence is the project manager demonstrating the value of project man...
- Q305. Budgets reserved for unplanned changes to project scope and cost are:...
- Q306. Which of the following is an example of a technique used in quantitative risk analysis?...
- Q307. At which stage of team development do members begin to work together, adjust work habits, ...
- Q308. Which of the following is an input to Control Scope?...
- Q309. The Process Group in which the internal and external stakeholders interact and influence t...
- Q310. One of the objectives of a quality audit is to:...
- Q311. The links between the processes in the Process Groups are often:...
- Q312. In Plan Risk Management, which of the management plans determines who will be available to...
- Q313. What name(s) is (are) associated with the Plan-Do-Check-Act cycle?...
- Q314. Which process involves identifying and documenting the logical relationships between proje...
- Q315. Which tool within the Perform Quality Control process identifies whether or not a process ...
- Q316. Which element does a project charter contain?
- Q317. Cost baseline is an output of which of the following processes?...
- Q318. What communication methods would a project manager use for overall effective project commu...
- Q319. Which of the following tools and techniques is used in the Verify Scope process?...
- Q320. Which technique is commonly used for the Perform Quantitative Risk Analysis process?...
- Q321. A project team member agrees to change a project deliverable after a conversation with an ...
- Q322. Which of the following is an output of the Conduct Procurements process?...
- Q323. Which of the following is an estimating technique that uses the values of parameters from ...
- Q324. Which cost estimate technique includes contingencies to account for cost uncertainty?...
- Q325. The project manager has the following information about the estimated duration for an acti...
- Q326. A recently hired project manager is looking for templates to use for projects on which the...
- Q327. What should a project manager consider to address the full delivery life cycle for large p...
- Q328. The following is a network diagram for a project. (Exhibit) The shortest non-critical path...
- Q329. A team was hired to develop a next generation drone. The team created a prototype and sent...
- Q330. Which quality tool incorporates the upper and lower specification limits allowed within an...
- Q331. The project leam is brainstorming on approaches to deliver the upcoming product launch for...
- Q332. A logical relationship in which a successor activity cannot start until a predecessor acti...
- Q333. Which cost estimate technique includes contingencies to account for cost uncertainty?...
- Q334. What tool or technique is used in the Collect Requirements process?...
- Q335. A project manager is working with the project sponsor to identify the resources required f...
- Q336. Which type of dependency used in the Sequence Activities process is sometimes referred to ...
- Q337. The chart below is an example of a: (Exhibit)
- Q338. A project manager is appointed full-time to a project and is given full-time administrativ...
- Q339. A technical project manager uses a directive approach with the team. Some team members are...
- Q340. Which tool or technique is an examination of industry and specific vendor capabilities?...
- Q341. Which of the following is a tool or technique used in the Acquire Project Team process?...
- Q342. Projects can be divided into phases to provide better management control. Collectively, wh...
- Q343. What should a project manager reference to understand where responsibility, accountability...
- Q344. Which of the following tasks focuses on decomposing work packages?...
- Q345. A project manager is performing a specific process and has..........is being referred to? ...
- Q346. The Monitoring and Controlling Process Group includes processes that:...
- Q347. During what project management process does the project manager invest the most effort int...
- Q348. A project manager is working in an environment where requirements are not very clear and m...
- Q349. What tool or technique uses an algorithm or statistical relationship between historical da...
- Q350. What is a hierarchically organized depiction of the identified project risks arranged by r...
- Q351. What are the key tools for managing project knowledge?...
- Q352. At which point of the project is the uncertainty the highest and the risk of failing the g...
- Q353. The process for performing variance analysis may vary, depending on:...
- Q354. Which factors should be considered for cross-cultural communication?...
- Q355. Which set of activities should a project manager use as part of the Develop Team process?...
- Q356. Tools and techniques used in Direct and Manage Project Work include:...
- Q357. Which is the correct formula for calculating expected activity cost for three-point estima...
- Q358. Which of the following is a tool and technique for Estimate Activity Durations?...
- Q359. A junior team member has been promoted to the position of project manager. The first task ...
- Q360. Which process identifies whether the needs of a project can best be met by acquiring produ...
- Q361. Projects can intersect with an organization's operations at various points during the prod...
- Q362. An output of the Manage Stakeholder Engagement process is:...
- Q363. Which of the following set of elements is part of an effective communications management p...
- Q364. Tools and techniques used in Direct and Manage Project Work include:...
- Q365. The number of potential communication channels for a project with 5 stakeholders is:...
- Q366. In what type of organizational structure does a project manager develop their role and wor...
- Q367. A project manager managing a cross-cultural virtual project team across several time zones...
- Q368. If a project manager effectively manages project knowledge, a key benefits is that:...
- Q369. Select three elements that apply to agile/ adaptive environments...
- Q370. Success is measured by benefits realization for a:...
- Q371. When executing a project, a recently hired subject matter expert (SME) who reviewed the ex...
- Q372. The technique of subdividing project deliverables into smaller, more manageable components...
- Q373. In Project Resource Management, which process uses recognition and rewards as a tool and t...
- Q374. A project manager engages a highly specialized resource who is in a different location and...
- Q375. Which of the following correctly lists the configuration management activities included in...
- Q376. A project manager should communicate to stakeholders about resolved project issues by upda...
- Q377. When does the project team determine which dependencies are discretionary?...
- Q378. The traditional organization chart structure that can be used to show positions and relati...
- Q379. Which enterprise environmental factors should be considered when creating a new procuremen...
- Q380. The following is a network diagram for a project. (Exhibit) The total float for the projec...
- Q381. Ensuring that both parties meet contractual obligations and that their own legal rights ar...
- Q382. What quantitative risk analysis technique is used to select the optimum course of action f...
- Q383. The process of prioritizing risks for further analysis or action is known as:...
- Q384. The creation of an internet site to engage stakeholders on a project is an example of whic...
- Q385. What process is included in Project Integration Management?...
- Q386. Which set of tools and techniques is useful for estimating activity durations for the proj...
- Q387. Which of the following set of elements is part of an effective communications management p...
- Q388. In which of the Risk Management processes is the project charter used as an input?...
- Q389. A project manager is determining the amount of contingency needed for a project. Which ana...
- Q390. The project management processes are usually presented as discrete processes with defined ...
- Q391. In a weak matrix, the project managers role is:...
- Q392. Which of the following is a tool or technique of the Define Activities process?...
- Q393. Which of the following is a schematic display of the project's schedule activities and the...
- Q394. A project is just beginning, and management creates a long list of potential stakeholders....
- Q395. Which is used to solicit proposals from prospective sellers?...
- Q396. The cost of nonconformance in a project includes:...
- Q397. A subject matter expert (SME) was recently assigned to a project to manage the new complia...
- Q398. At the beginning of an iteration, the team will work to determine how many of the highest-...
- Q399. Which type of analysis would be used for the Plan Quality process?...
- Q400. Which enterprise environmental factors should be considered when creating a new procuremen...
- Q401. Which is an enterprise environmental factor?
- Q402. Which tool within the Perform Quality Control process identifies whether or not a process ...
- Q403. Which three of the following are the most widely used techniques that a business analyst s...
- Q404. According to PMBOK, the definition of Plan Risk Management is:...
- Q405. What can the cost management plan be established?...
- Q406. A project manager managing a cross-cultural virtual project team across several time zones...
- Q407. Which of the Perform Quality Assurance tools and techniques may enhance the creation of th...
- Q408. What is the definition of Direct and Manage Project Execution?...
- Q409. Which of the following processes are within the Initiating Process Group?...
- Q410. The project manager is leading a construction project that has been ongoing for eight year...
- Q411. Project management processes are:
- Q412. The key benefit of the Monitoring and Controlling Process Group is the ability to:...
- Q413. In the Define Activities process, the schedule management plan is used to:...
- Q414. The most appropriate project life cycle model for an environment with a high level of chan...
- Q415. An input to the Collect Requirements process is the:...
- Q416. The Perform Integrated Change Control process occurs in which Process Group?...
- Q417. An important project stakeholder has low risk tolerance. Which type ot communication shoul...
- Q418. How should a stakeholder who is classified as high power and low interest be grouped in a ...
- Q419. A project manager read the initial contract when a project was started. The contract state...
- Q420. Using parametric estimating, if an assigned resource is capable of producing 120 units per...
- Q421. A project requires a component with well-understood specifications. Performance targets ar...
- Q422. Which of the following are an enterprise environmental factor that can influence the Ident...
- Q423. Which of the following strategic considerations often results in project authorization?...
- Q424. A project manager managing a cross-cultural virtual project team across several time zones...
- Q425. An employee was hired to work on ongoing, repetitive activities in the accounting departme...
- Q426. When a control chart is used to monitor performance of a process, which of the following w...
- Q427. What is the total float of the critical path?
- Q428. Which tool or technique is used to develop the human resource management plan?...
- Q429. Which of the following is an output of Close Procurements?...
- Q430. During a retrospective, the team finds that all of the user stories are not complete. What...
- Q431. Scope, schedule, and cost parameters are integrated in the:...
- Q432. Which process in Project Time Management includes reserve analysis as a tool or technique?...
- Q433. Which type of dependency is established based on knowledge of best practices within a part...
- Q434. Which technique should a project manager use in a situation in which a collaborative appro...
- Q435. Which is a list of organizational systems that may have an impact on a project?...
- Q436. Organizational planning impacts projects by means of project prioritization based on risk,...
- Q437. Two resources are performing a peer review of an artifact. What should be the outcome of t...
- Q438. A project team member is estimating the cost of an activity and is checking documentation ...
- Q439. Which enterprise environmental factors are considered during cost estimating?...
- Q440. Which of the following must be included in the risk register when the project manager comp...
- Q441. Which risk management strategy seeks to eliminate the uncertainty associated with a partic...
- Q442. Impacts to other organizational areas, levels of service, and acceptance criteria are typi...
- Q443. Which type of contract is most commonly used by buying organizations because the price for...
- Q444. The project management processes presented in the PMBOK Guide should:...
- Q445. What should the project manager use to evaluate the politics and power structure among sta...
- Q446. Select two key benefits of the Control Procurements process. (Choose two.)...
- Q447. Work performance information is an input to which of the following processes?...
- Q448. Which three of the following are key traits of a project leader? (Choose three)...
- Q449. A process is defined as:
- Q450. Project or phase closure guidelines or requirements, historical information, and the lesso...
- Q451. During project selection, which factor is most important?...
- Q452. Which action should the project manager take after the team finishes executing the scope?...
- Q453. Which of the following strategies is used to deal with risks that may have a negative impa...
- Q454. A new game development process must have three versions. Each version is to be developed i...
- Q455. Updates to organizational process assets such as procurement files, deliverable acceptance...
- Q456. The project budget is set at $150,000. The project duration is planned to be one year. At ...
- Q457. What important qualities should project managers possess for strategic and business manage...
- Q458. Analyzing activity sequences, durations, resource requirements, and schedule constraints f...
- Q459. What process group includes processes performed to complete work to satisfy the project re...
- Q460. What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual...
- Q461. The table represents the possible durations of a specific project task. (Exhibit) Using th...
- Q462. Which of the following is an example of facit knowledge?...
- Q463. A technique used to determine the cause and degree of difference between baseline and actu...
- Q464. Which type of management focuses on ensuring that projects and programs are reviewed to pr...
- Q465. After Define Activities and Sequence Activities, the next process is:...
- Q466. Which process is engaged when a proiect learn inember makes a change to project budget wit...
- Q467. Which Process Group includes the Manage Stakeholder Engagement process?...
- Q468. The following is a network diagram for a project. (Exhibit) What is the critical path for ...
- Q469. Which tool uses an algorithm based on historical data to calculate cost?...
- Q470. Which type of contract gives both the seller and the buyer flexibility to deviate from per...
- Q471. Which tasks should a project manager perform in order to manage the project schedule effec...
- Q472. Which of these is true of a project schedule?
- Q473. The Verify Scope process is primarily concerned with:...
- Q474. A project team submits a weekly progress report to the project manager. The project manage...
- Q475. A project manager is working on project cost management. The following information is curr...
- Q476. A contractor has provided hands-on training to a team member on new equipment that has bee...
- Q477. The degree of uncertainty an entity is willing to take on in anticipation of a reward is k...
- Q478. Team performance assessments is an output of which of the following processes?...
- Q479. The Process Group that involves coordinating people and resources, as well as integrating ...
- Q480. When should Project Risk Management be conducted?...
- Q481. An input required to develop a preliminary project scope statement is:...
- Q482. A sponsor asks a project manager to provide a project ' s expected total costs based on it...
- Q483. Which input to Collect Requirements is used to identify stakeholders who can provide infor...
- Q484. What are the three components of a work breakdown structure (WBS) dictionary? (Choose thre...
- Q485. The project manager has requested all expert team members to complete an anonymous questio...
- Q486. Which of the following must be included in the risk register when the project manager comp...
- Q487. Enterprise environmental factors are an input to which process?...
- Q488. A project manager builds consensus and overcomes obstacles by employing which communicatio...
- Q489. One of the objectives of a quality audit is to:...
- Q490. Which of the Project Time Management processes analyzes activity sequencing, durations, re...
- Q491. A project manager can choose from several techniques to resolve conflicts between team mem...
- Q492. Calculate the Schedule Performance Index (SPI) based on the following information: earned ...
- Q493. A project manager needs to tailor the Project Cost Management process. Which consideration...
- Q494. The following is a network diagram for a project. (Exhibit) The free float for Activity E ...
- Q495. Under which type of contract does the seller receive reimbursement for all allowable costs...
- Q496. Creating the project scope statement is part of which process?...
- Q497. A tool and technique used during the Define Scope process is:...
- Q498. A firm contracted an event management company to conduct the annual sales day event. The a...
- Q499. Plan-do-check-act is also known as:
- Q500. What is the process of determining the stakeholders impacted by a business problem or oppo...
- Q501. Which Perform Quality Control tool graphically represents how various elements of a system...
- Q502. Which change request is an intentional activity that realigns the performance of the proje...
- Q503. A benefit of using virtual teams in the Acquire Project Team process is the reduction of t...
- Q504. A project is in its final stages when a competitor releases a similar product. This could ...
- Q505. Due to today ' s competitive global market, organizations require more than technical proj...
- Q506. What is the equation to calculate cost variance (CV)?...
- Q507. Which Plan Schedule Management tool or technique may involve choosing strategic options to...
- Q508. Which of the following activities are included as part of a project manager's responsibili...
- Q509. Plan-do-check-act is also known as:
- Q510. Plan Communications Management develops an approach and plan for project communications ba...
- Q511. Which action should a project manager take to ensure that the project management plan is e...
- Q512. Company A has just been notified about a new legal requirement for its business operations...
- Q513. Perform Quality Control is accomplished by:
- Q514. A project using the agile/adaptive approach has reached the Project Integration Management...
- Q515. An organization is faced with increasing demand from the board of directors. They say budg...
- Q516. Due to today's competitive global market, organizations require more than technical projec...
- Q517. What is the role of project management in terms of organizational strategy?...
- Q518. Sensitivity analysis is typically displayed as a/an:...
- Q519. Plan Schedule Management is a process in which Knowledge Area?...
- Q520. A project ' s aim, from a business perspective, is moving an organization from one level t...
- Q521. The project manager released a report. A few stakeholders express the view that the report...
- Q522. A key project team member complains about being left out of the communication loop. In ord...
- Q523. What process is included in Project Schedule Management?...
- Q524. Which piece of information is part of the WBS Dictionary?...
- Q525. Given the following information. Activity A takes one week. Activity B takes three weeks. ...
- Q526. A project manager was assigned to a project to implement a manufacturing system in a food ...
- Q527. The following is a network diagram for a project. (Exhibit) The free float for Activity E ...
- Q528. An input to the Perform Quantitative Risk Analysis process is the:...
- Q529. In the Plan Stakeholder Management process, expert judgment is used to:...
- Q530. The following is a network diagram for a project. (Exhibit) The total float for the projec...
- Q531. What can the project manager find among the factors that could lead a project to be tailor...
- Q532. Which of the following sets are inputs to the Collect Requirements process?...
- Q533. A large portion of a projects budget is typically expended on the processes in which Proce...
- Q534. Which tools and techniques will a project manager use to develop a project charter?...
- Q535. In a functional organization, the director of an important stakeholder business group expr...
- Q536. A project team is brainstorming about the best methods and practices to adopt for an upcom...
- Q537. What is the primary benefit of meeting quality requirements?...
- Q538. Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools an...
- Q539. The milestone list is an input to which process from the Planning Process Group?...
- Q540. Exhibit A is an example of which of the following types of Sequence Activities? (Exhibit)...
- Q541. The only Process Group that comprises processes that typically occur from the beginning to...
- Q542. A program consists of four agile teams. Each team has a separate daily standup. Later each...
- Q543. Which is an example of analogous estimating?
- Q544. Which statement describes the various purposes of project scheduling?...
- Q545. In the last two iterations, a project team failed to deliver all of the stories on time. W...
- Q546. How can a project manager determine if the project activities comply with organizational a...
- Q547. During which process does a project manager review all prior information to ensure that al...
- Q548. The features and functions that characterize a result, product, or service can refer to:...
- Q549. Under which type of contract does the seller receive reimbursement for all allowable costs...
- Q550. Which is an example of an internal enterprise environmental factor?...
- Q551. When sequencing activities, what does the common acronym FF stand for?...
- Q552. Two members of the team are having a conflict..............or partially resolve the proble...
- Q553. A tool and technique used in the Develop Project Charter process is:...
- Q554. A new project manager has been assigned to an ongoing project. What will the project manag...
- Q555. The process of identifying and documenting project roles, responsibilities, required skill...
- Q556. Which Process Group typically consumes the bulk of a project ' s budget?...
- Q557. What is the discipline that focuses on the interdependences between projects to determine ...
- Q558. The total of the planned value (PV) is also known as:...
- Q559. Which of the following reduces the probability of potential consequences of project risk e...
- Q560. Within project integration management, the statement of work (SOW) references which aspect...
- Q561. In order to detect quality issues earlier in the project life cycle, the project manager i...
- Q562. Stakeholder identification and engagement should begin during what phase of the project?...
- Q563. What is the discipline that focuses on the interdependencies between projects to determine...
- Q564. Which type of project life cycle uses an iteration plan?...
- Q565. In which Knowledge Area is the project charter developed?...
- Q566. Which type of probability distribution is used to represent uncertain events such as the o...
- Q567. Which are the main objectives of Project Risk Management?...
- Q568. An important project stakeholder has low risk tolerance. Which type ot communication shoul...
- Q569. A project manager is calculating the current budget. The earned value (EV) of the project ...
- Q570. Which tool or technique is used in the Plan Scope Management process?...
- Q571. In a project, total float measures the:
- Q572. Which of the following types of a dependency determination is used to define the sequence ...
- Q573. Which of the following are outputs of define scope process in project scope management...
- Q574. A team is working on a project using an adaptive approach. During project execution, the p...
- Q575. Company A's accountant sends notification about a change in the company's tax classificati...
- Q576. The completion of the project scope is measured against the:...
- Q577. A business analyst needs to ensure the project team understands the most critical roles an...
- Q578. To please the customer, a project team member delivers a requirement which is uncontrolled...
- Q579. Administer Procurements is part of which Process Group?...
- Q580. The Plan Stakeholder Management process belongs to which Process Group?...
- Q581. In the Control Quality process, which tools and techniques techniques can be applied to ve...
- Q582. A project manager held a meeting and listed all team members' ideas for improving the prod...
- Q583. When an activity cannot be estimated with a reasonable degree of confidence, the work with...
- Q584. Which input to the Plan Risk Management process provides information on high-level risks?...
- Q585. A given schedule activity is most likely to last four weeks. In a best-case scenario, the ...
- Q586. The Identify Stakeholders process is found in which Process Group?...
- Q587. What is an objective of the Develop Project Team process?...
- Q588. The purpose of the Project Communications Management Knowledge Area is to:...
- Q589. A newly developed project team is working together, building trust and adjusting its work ...
- Q590. Change request status updates are an output of which process?...
- Q591. Which document defines how a project is executed, monitored and controlled, and closed?...
- Q592. What is the common factor among portfolios, programs, and projects, regardless of the hier...
- Q593. A project manager has to share a status report with a new stakeholder and is trying to det...
- Q594. A project team is working on relocating offices to another building and providing new furn...
- Q595. The degree, amount, or volume of risk that an organization or individual will withstand is...
- Q596. What process is used to identify quality requirements and/or standards for a project and i...
- Q597. A project team conducts regular standup meetings to keep everyone updated on what each one...
- Q598. A company has implemented an adaptive project management framework for a new project. When...
- Q599. Overlooking negative stakeholders can result in a/an:...
- Q600. Change requests are processed for review and disposition according to which process?...
- Q601. What conflict resolution technique involves delaying the issue or letting others resolve i...
- Q602. The Agile principle "welcome changing requirements, even late in development" relates to w...
- Q603. Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?...
- Q604. A project manager is determining the amount of contingency needed for a project. Which ana...
- Q605. Which estimating technique uses the actual costs of previous similar projects as a basis f...
- Q606. Plan Risk Management is the process of defining how to:...
- Q607. In which phase of team building activities do team members begin to work together and adju...
- Q608. In which of the Risk Management processes is the project charter used as an input?...
- Q609. A process is defined as:
- Q610. Which action is included in the Control Costs process?...
- Q611. A project ' s business analyst has to understand the newly acquired technology and the imp...
- Q612. Which components of the project management plan are inputs used when creating the stakehol...
- Q613. Which type of estimating is used to improve the accuracy of an activity's duration?...
- Q614. An organization is interested in improving the ways of working for their teams. They are i...
- Q615. What is the process of ensuring that project resources are assigned and available?...
- Q616. Which of these is true project integration management?...
- Q617. Inputs to the Plan Schedule Management process include:...
- Q618. Which Perform Quality Assurance tool or technique is used to identify a problem, discover ...
- Q619. A project team submits a weekly progress report to the project manager. The project manage...
- Q620. The following is a network diagram for a project. (Exhibit) How many possible paths are id...
- Q621. A logical relationship in which a successor activity cannot start until a predecessor acti...
