Join the discussion
Add Comments
- Other Question (202q)
- Q1. A new Sprint starts immediately following the previous Sprint....
- Q2. The measure of productivity of a Kanban team is:...
- Q3. According to the Agile Manifesto, which of the following describes the more valued items?...
- Q4. Agile Earned Value Management (EVM) would be a valuable technique for managing a project b...
- Q5. Why should an agile coach model agile principles and behaviors, become self-aware, and be ...
- Q6. What should an agile practitioner do to ensure that the end product meets business require...
- Q7. What is the order the hierarchy of product definition? (Exhibit)...
- Q8. How can an agile team working on a new product ensure alignment with external stakeholders...
- Q9. What Agile planning artifact is created by the Product Owner and the development team?...
- Q10. Sequence the activities that occur in a Retrospective meeting. (Exhibit)...
- Q11. A product owner asks a newly formed scrum team how many story points will be completed in ...
- Q12. A team is creating a highly marketed, time-sensitive product. The agile coach is concerned...
- Q13. This Agile methodology's properties include Focus, Osmotic Communication and Project Safet...
- Q14. An agile team is preparing a release plan for a project. What information will the team ne...
- Q15. Which type of estimate refers to estimating a story based on its relationship to one or mo...
- Q16. An agile team is preparing a release plan for a project. What information will the team ne...
- Q17. A new learn member asks what changes could accelerate a change to the project plan. What s...
- Q18. A mature agile team welcomes a new member. Due to poor experiences with a previous team, t...
- Q19. Which of the following is NOT one of the 12 core practices of XP?...
- Q20. Who is responsible for the Project Plan and Gantt Chart in Scrum?...
- Q21. Which of the following defines Elapsed Time?
- Q22. Senior management is frustrated at the lack of a detailed implementation plan that shows e...
- Q23. During a current sprint a learn member asks permission horn the scrum master lo investigat...
- Q24. A scrum master is part of a project team using technologies overseen by the IT department....
- Q25. The purpose of the iteration retrospective is to:...
- Q26. Agile Earned Value Management (EVM) would be a valuable technique for managing a project b...
- Q27. Which of the following is most appropriate to always participate in Planning Poker?...
- Q28. Team velocity is used to:
- Q29. The best approach to estimate the work on a project when using story points is to have:...
- Q30. Refactoring is a key way of preventing technical debt....
- Q31. During its first sprint a new scrum team realizes that it has insufficient team members wi...
- Q32. What is a high-level representation of the features or themes that are to be delivered in ...
- Q33. Which of the following factor will not assist in improving the project velocity?...
- Q34. A learn member 15 stressed due to a heavy workload, while other team members have some sla...
- Q35. Order the 5 focusing steps of the Theory of Constraints. (Exhibit)...
- Q36. A ScrumMaster consistently holds Daily Scrums and keeps them to 15 minutes or less. The Sc...
- Q37. Which of the following are TRUE about the Sprint Retrospective? (Choose two.)...
- Q38. Midway through a sprint. a scrum team member advises the team of a new requirement Dial ma...
- Q39. A full cycle of design-code-verifyrelease practiced by extreme Programming (XP) teams is c...
- Q40. Midway through a sprint. a scrum team member advises the team of a new requirement Dial ma...
- Q41. The agile team disagrees with the business stakeholders on completing some epics. What cou...
- Q42. The product owner of a learn starts the iteration review with a quick walkthrough of the i...
- Q43. A development team and product owner disagree on a user story in the product backlog. What...
- Q44. The most powerful capability of Scrum teams is that they:...
- Q45. An executive requests information regarding a sprint status. What action should the produc...
- Q46. Midway through a sprint the scrum master identifies that reassigning a certain task could ...
- Q47. During iteration planning, it was determined that an epic should be decomposed. What was t...
- Q48. During Sprint Planning, the architect is constanly estimating higher than everyone else, a...
- Q49. The purpose of "setting the stage'' in a project retrospective is to:...
- Q50. A company is starting to introduce Agile practices, and the project manager has been asked...
- Q51. In Agile risk management, a risk burndown chart is best used to:...
- Q52. Which of the following best represents both a principle of the Agile manifesto and a Lean ...
- Q53. A story point is the:
- Q54. A legal department representative contacts the scrum master because white the projects bud...
- Q55. What are the primary outputs of a release planning session?...
- Q56. All of the following occur in the second half of the Sprint planning meeting EXCEPT:...
- Q57. Which of the following statements is an accurate value statement of the Agile Manifesto?...
- Q58. Drag and Drop Question Match the definitions (on the right) to each of the characteristics...
- Q59. On what should Agile estimates be based?
- Q60. In Scrum, who is responsible for managing the team?...
- Q61. In Agile risk management, a risk burndown chart is best used to:...
- Q62. While struggling to take ownership of delivery, an agile team fails to keep up with its sp...
- Q63. During a retrospective meeting, a team develops a large list of initiatives. All will have...
- Q64. Which of the following is NOT one of the 12 core practices of XP:...
- Q65. Based on the following information, determine the number weeks until the next release. (Ex...
- Q66. In reference to Scrum, each sprint should produce:...
- Q67. An agile practitioner wants to communicate the effect of technical debt on the project Wha...
- Q68. Risk exposure is the:
- Q69. During the review session, the product owner discovers that the user interface has a respo...
- Q70. In Scrum, the definition of "done" is created by everyone EXCEPT:...
- Q71. When facilitated and managed well, the primary benefits of a project retrospective should ...
- Q72. In a Lean Software Development environment, the Project Leader strives to eliminate:...
- Q73. The executive leadership wants to understand ways to better deliver on time and on budget....
- Q74. A project team identifies a number of technical challenges with features in the next sprin...
- Q75. What is the name of this facilitated process? One or more team members sequence the produc...
- Q76. An agile team is working on the first sprint, and have already planned the second and thir...
- Q77. For the best results in an Agile project, customers should:...
- Q78. The purpose of the iteration retrospective is to:...
- Q79. Who typically has the best insight into task execution?...
- Q80. Agile Earned Value Management (EVM) would be a valuable technique for managing a project b...
- Q81. Acceptance tests of user stories are specified by the:...
- Q82. A team's technical lead believes that manual testing tasks should be conducted by junior t...
- Q83. During a planning session, four out five team members vote to include eight story points i...
- Q84. A company is moving into a new space and is determining the best configuration for offices...
- Q85. Following chart lists stories for a release of an Agile project; If the team completes Sto...
- Q86. The key elements of a user story in Agile development are:...
- Q87. Due to its complexity, a new team member struggles with developing a concise user story. W...
- Q88. Spike solutions are appropriate when:
- Q89. An agile team has only one database administrator with the necessary knowledge of database...
- Q90. Personas are used in Agile requirements to depict which type of user?...
- Q91. During backlog refinement meeting, the new developer on the team asks the product owner to...
- Q92. Classes of Services in Kanban are used to:
- Q93. Who updates work remaining during the Sprint?
- Q94. A company has decided to combine Iwo similar products consisting of multiple teams into on...
- Q95. Based on the chart, what is the current status of the iteration when comparing story point...
- Q96. A high-performance Agile team:
- Q97. When estimating initial velocity, the team should most likely:...
- Q98. During a sprint review, the product owner identifies a required improvement for a feature'...
- Q99. eXtreme Programming (XP) teams strive to avoid:...
- Q100. According to the Agile Manifesto, which of the following describes the more valued items?...
- Q101. When comparing communication styles, which of the following are true?...
- Q102. A new product owner shares the product vision during the team launch event. The team asks ...
- Q103. During the iteration planning of a newly onboarded agile team, the product owner adds a se...
- Q104. CRUD is an acronym that defines a way to split stories. What does CRUD stand for?...
- Q105. A development team for a small company experiences long delays between product completion ...
- Q106. Agile team A struggles to deliver committed stories due to technical dependencies with tea...
- Q107. An Agile team best ensures product quality through:...
- Q108. During the daily standup meeting, a team member states that an issue has been encountered....
- Q109. Agile Earned Value Management (EVM) would be a valuable technique for managing a project b...
- Q110. When an Agile project team receives an "emergency request" during an iteration, which is t...
- Q111. Simple Design, Pair Programming, Test-Driven Development, Design Improvement are all pract...
- Q112. When is the ideal time to hold a retrospective?...
- Q113. A ScrumMaster:
- Q114. The velocity chart, storyboard, burndown chart, and impediment list are often communicated...
- Q115. In the Lean process, the focus is on:
- Q116. The ScrumMaster notices repeated friction between two team members in the Daily Scrum meet...
- Q117. An agile team is unable to complete all its planned sprint user stories, which results in ...
- Q118. During an iteration, an agile team discovers infrastructure requirements that were not ini...
- Q119. During product development, changes in technology and regulations require the team to reas...
- Q120. John and Joseph are working in the same room. John is programming and Joseph is having som...
- Q121. A scrum team has conducted regular retrospectives to discuss immediate concerns and the im...
- Q122. A product owner feels that the last sprint failed to sufficiently deliver that was valuabl...
- Q123. On what should Agile estimates be based?
- Q124. The primary purpose of a Sprint retrospective is for the team to:...
- Q125. Match the response options to each level of conflict. (Exhibit)...
- Q126. A team identifies the number of threats and lists them in the order in which they were ide...
- Q127. A team identifies the number of threats and lists them in the order in which they were ide...
- Q128. An agile team has been given a complex project with a basic set of requirements which need...
- Q129. A newly formed scrum team wants to foster an environment of transparency and experimentati...
- Q130. Which of the following is an example of a visual aid used in Lean-Agile software developme...
- Q131. An agile team's client has been asked to expedite the delivery of the next release. By del...
- Q132. Drag and Drop Question When reading a burn-down chart, what does each status measurement s...
- Q133. After three iterations, the problems impeding an Agile team appear to be similar in nature...
- Q134. Based upon this Burndown chart, is this project ahead of schedule or behind schedule? (Exh...
- Q135. The Kaizen philosophy is change:
- Q136. When introducing agile processes to a company, a quality assurance (QA) manager resists an...
- Q137. A "Scrum of Scrums" meeting is:
- Q138. What should an agile practitioner do to ensure that the end product meets business require...
- Q139. Which type of risk analysis does an Agile team use to identify risks on their project?...
- Q140. What is one of the benefits of incremental delivery?...
- Q141. What are three processes used to begin an Agile project?...
- Q142. This artifact contains release names with expected dates and includes major features, clie...
- Q143. In the first part of the Sprint Planning meeting, what is NOT accomplished?...
- Q144. Which of the following statements is true for measuring team velocity?...
- Q145. A scrum master assumes a project that is essential to organizational growth. The project i...
- Q146. During planning sessions, an agile practitioner notices that some team members do not shar...
- Q147. In Agile risk management, a risk burndown chart is best used to:...
- Q148. An executive sponsor of a new scrum team actively attends scrum ceremonies. How does this ...
- Q149. What is the sequence of Tuckman's stages of team formation and development progress?...
- Q150. The customer needs assistance m determining the efficiency of a set of process activities ...
- Q151. Based on the following figure, during Iteration 5, there was an increase in story point va...
- Q152. When does a Sprint get canceled or end early?
- Q153. Suppose your team velocity is 8 story points, and the product backlog items are ordered by...
- Q154. In agile approaches, negotiation is viewed as:...
- Q155. The agile practitioner has determined that two different team members are working on addre...
- Q156. An agile project manager is planning the initial scope, schedule, and cost range estimates...
- Q157. Continuous integration ensures that a product is:...
- Q158. At a strategic level, what is the most appropriate way for an Agile team to estimate a pro...
- Q159. Match each Agile requirement type (on the left) to its definition (on the right). (Exhibit...
- Q160. Which one is NOT a level of need in the Kano Model?...
- Q161. Retrospectives provide an opportunity for the team to:...
- Q162. What is the first thing that a team should do to estimate user stories for a project?...
- Q163. A development team for a small company experiences long delays between product completion ...
- Q164. Pick the two PMLC models that are based upon the Agile Project Management (APM) approach:...
- Q165. Drag and Drop Question Pick which 3 activities are the responsibilities of the Scrum Maste...
- Q166. While attending a conference, an agile practitioner learns of a new user interface (Ul) fr...
- Q167. The most powerful capability of Scrum teams is that they:...
- Q168. During a retrospective, the agile practitioner discovers that a team member's process impr...
- Q169. A project manager is concerned that the team has misaligned expectations with some stakeho...
- Q170. What can a team use to prioritize stories?
- Q171. Who can cancel a Sprint?
- Q172. According to the Agile Manifesto, which of the following describes the more valued items?...
- Q173. A ScrumMaster consistently holds Daily Scrums and keeps them to 15 minutes or less. The Sc...
- Q174. What is the Japanese business philosophy focused on making constant improvements?...
- Q175. How should an agile project leader interact with the product owner?...
- Q176. When is the best time to perform Earned Value Measurement (EVM) in Agile projects?...
- Q177. The following is a picture of which of the following Information Radiators? (Exhibit)...
- Q178. One of your stakeholder is interested in viewing the project progress but he is not intere...
- Q179. A project manager is concerned that the team has misaligned expectations with some stakeho...
- Q180. The ___________ the technical debt means the ________ the intrinsic quality?...
- Q181. Which of the following best describes a core belief of Agile?...
- Q182. While attending a conference, an agile practitioner learns of a new user interface (Ul) fr...
- Q183. Which of these statements is NOT correct about Ideal time and Calendar time?...
- Q184. User stories are temporary artifacts. They are considered relevant until the:...
- Q185. A scrum master is part of a project team using technologies overseen by the IT department....
- Q186. Assuming one-week iterations and a team of four developers, how many iterations will it ta...
- Q187. Which one is NOT a reason to perform a Spike?
- Q188. Who is responsible for determining the business value of each feature?...
- Q189. Since the last iteration, the team has grown from six members to 14 members. As a result, ...
- Q190. During sprint retrospectives, some team members are very vocal and tend to dominate the co...
- Q191. An agile team is beginning a new release. Things are progressing a little slower than they...
- Q192. A ScrumMaster consistently holds Daily Scrums and keeps them to 15 minutes or less. The Sc...
- Q193. In an Agile approach, project values are most effectively implemented when they are determ...
- Q194. The following is a picture of which of the following Information Radiators? (Exhibit)...
- Q195. At the end of a product development phase, an agile project team confirms that all tests h...
- Q196. During a sprint, the team encounters a technical problem that becomes an impediment to com...
- Q197. _____________ an estimate refers to estimating a story based on its relationship to one or...
- Q198. A project team is distributed across multiple countries, and they are having issues agreei...
- Q199. Based on the following information, determine the number weeks until the next release. (Ex...
- Q200. This Emertxe Project Management (MPx) approach is when neither a goal nor solution is clea...
- Q201. Which type of story would be used when an estimate is not available due to lack of knowled...
- Q202. It is not possible to have a fixed price contract in Agile....
