Join the discussion
Add Comments
- Other Question (586q)
- Q1. Which of the following regarding project charter is FALSE?...
- Q2. A newly appointed product owner is working with a project team that is using agile for the...
- Q3. During a weekly project meeting, the team members and stakeholders complain about receivin...
- Q4. The use of scarce resources must be decided upon with functional managers before it causes...
- Q5. Product analysis uses which of the following techniques EXCEPT:...
- Q6. Organizational theory is a tool used in which Project Human Resource Management process?...
- Q7. Oftentimes when a project is terminated, senior managers will replace the project manager ...
- Q8. A company's project management office (PMO) has started to implement iterative tools A pro...
- Q9. Which tool or technique is used in Close Procurements?...
- Q10. You are in the process of creating a project plan for the launch of a new drug. While crea...
- Q11. A key stakeholder has validated the feasibility of an idea that will bring significant cos...
- Q12. Detailed design has begun on a firm fixed price (FFP) contract, and the statement of work ...
- Q13. A project is starting its sixth iteration out seven. During the daily meeting, a team memb...
- Q14. You are the project manager on a project to improve traffic flow in the company's parking ...
- Q15. After delivery of a marketing logo, the customer demands a revision because they believe t...
- Q16. Which of the following scheduling techniques focuses on managing buffer activity durations...
- Q17. A new payment system is being built using agile principles During a customer demonstration...
- Q18. A project manager has been assigned to a global project involving regulatory bodies, gover...
- Q19. During a projects' planning phase, the high and fluctuating price of raw materials was ide...
- Q20. A project manager identifies a risk and its possible impact. The project manager notifies ...
- Q21. A project manager is assigned to a global project with dispersed team members. Previously,...
- Q22. An electronics firm authorizes a new project to develop a faster, cheaper, and smaller lap...
- Q23. A project manager is managing a hybrid project A stakeholder has directly contacted a team...
- Q24. Correlated and contextualized information on how closely the scope is being maintained rel...
- Q25. Which changes occur in risk and uncertainty as well as the cost of changes as the life cyc...
- Q26. As a project manager, you realize that handling Project Stakeholder expectations is an imp...
- Q27. A healthcare company is in the process of deploying an innovative healthcare solution glob...
- Q28. Having worked previously on projects as a team member, you are pleased to now be the proje...
- Q29. Company A wants to subcontract the installation of a factory's building management system ...
- Q30. In order to let the project sponsor know the percentage of cost variance of your project, ...
- Q31. Quality control charts show a characteristic of the product or service against:...
- Q32. A CEO of a general contracting company urgently asks the project manager to sign up two pr...
- Q33. A project manager is assigned to a project that is in progress. In which of the following ...
- Q34. Which Project Time Management process includes bottom-up estimating as a tool or technique...
- Q35. In organizing a project, a project manager must deal with conflict. Which statement is TRU...
- Q36. Which Perform Quality Assurance tool or technique is used to identify a problem, discover ...
- Q37. The detailed project scope statement includes all of the following EXCPET:...
- Q38. A company has started a drainage improvement project to avoid flooding due to heavy rainfa...
- Q39. In which Knowledge Area is the project charter developed?...
- Q40. A project manager is working on the delivery of a solution that needs to be deployed to th...
- Q41. An agile team wants to maximize the work delivered for the upcoming project that involves ...
- Q42. You are using the three-point estimating technique to estimate the duration of a schedule ...
- Q43. An agile project is approaching its first release date, and the product will be supported ...
- Q44. Several components of an expensive manufacturing project have been returned by the custome...
- Q45. Which one of the following statements best characterizes an activity cost or duration esti...
- Q46. Phase exits, kill points and stage gates are used for what purpose?...
- Q47. Which of the following statements are FALSE regarding project funding requirements?...
- Q48. An issue will cause the project team to miss a critical milestone. The project manager rea...
- Q49. You are responsible for launch operations of different NASA satellites. Your role is that ...
- Q50. A team is ready to start working on a project with a customer who was very difficult to wo...
- Q51. Configuration identification, configuration status accounting, and configuration verificat...
- Q52. A major assumption of all network scheduling methods is that activity durations must be __...
- Q53. It is important on all projects to determine when and how human resources will be met. Ass...
- Q54. Which of the following ensures that requested changes to deliverables are thoroughly consi...
- Q55. A project manager is leading a hybrid project. The only available resources that have expe...
- Q56. Adding 5 people to a 4 person team increases the communication channels by a factor of:...
- Q57. Perform Integrated Change Control is the process of:...
- Q58. While preparing the resource management plan, a project manager learns that me organizatio...
- Q59. An earthquake occurs at the site of a manufacturing plant construction project. This affec...
- Q60. A senior engineer notifies the project manager that there will be a delay in the product's...
- Q61. As part of the strategic plan, a company decides to implement a new software platform to m...
- Q62. During a weekly status meeting, a key stakeholder complains that quality standards for som...
- Q63. Work performance information is an output of which process?...
- Q64. A project manager is running a company-wide project involving different business units Dur...
- Q65. The customer has decided that he wants blue walls instead of gray. You have not painted th...
- Q66. A project manager on a construction project includes a line item in the budget for insuran...
- Q67. A project manager is working on a large IT project. During a review for one of the deliver...
- Q68. Which tool or technique measures performance of the project as it moves from project initi...
- Q69. A project manager has noticed that a specific team member rarely contributes or shares opi...
- Q70. Which of the following choices is a contract closure tool or technique?...
- Q71. Which of the following includes how requirements activities will be planned, tracked, and ...
- Q72. Which type of organizational structure is displayed in the diagram provided? (Exhibit)...
- Q73. You are the Project Manager on a project where $4M US will be spent on procuring telecom e...
- Q74. A construction project to build a fish hatchery is in execution. The operations group noti...
- Q75. A new project stakeholder is identified who has interest in, but little authority or influ...
- Q76. Recognizing the importance of preparing a stakeholder management plan, you met with your t...
- Q77. The chances for successful completion of a multidisciplinary project are increased if proj...
- Q78. The project manager is having difficulty communicating with one of the team members The te...
- Q79. A junior project manager with experience in predictive projects has joined a company that ...
- Q80. A project team member is having difficulty delivering assigned tasks for a project that is...
- Q81. Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), a...
- Q82. Which of the following makes changes to formally control documentation to reflect modified...
- Q83. A project is being executed in multiple phases. Midway through, the customer wants to brin...
- Q84. A multimillion-dollar project has started and is in the execution phase. A local regulator...
- Q85. Calculate the standard deviation for the following: Pessimistic=20, Optimistic=10, Realist...
- Q86. A project manager is leading an automation project. The project team is colocated and incl...
- Q87. Eight people have been working on a project for an extended period of time. The scope has ...
- Q88. There are a number of different earned value management rules of performance measurement t...
- Q89. Crosswind Custom Homes is building a customer's dream house. However, rain has delayed the...
- Q90. The CPI on your project is 0.44, which means that you should______________...
- Q91. While identifying risks for a new construction project, you discover that a chemical you a...
- Q92. During a retrospective review, many project team members say they are not completing tasks...
- Q93. An electronics firm authorizes a new project to develop a faster, cheaper, and smaller lap...
- Q94. When should quality planning be performed?
- Q95. A project manager is assigned to a time-bound internal project on quality improvement Duri...
- Q96. A project sponsor commonly asks the project manager to skip project retrospectives due to ...
- Q97. Which of the following statements are false?
- Q98. Buyers use a variety of methods to provide incentives to a seller to complete work early o...
- Q99. The scope of a project is to replace the street signs within a 10-km radius. The client do...
- Q100. A hospital is running a project for one of their internal critical systems to manage billi...
- Q101. A project manager brings in a new team member from an agile environment to work in a predi...
- Q102. The erection of foundation formwork before the placement of foundation concrete would be a...
- Q103. The project planning is progressing. The team has involved the accounting department to se...
- Q104. Which index is the calculated projection of cost performance that must be achieved on the ...
- Q105. Activity A is worth $300, is 100% complete, and actually cost $350. Activity B is worth $1...
- Q106. While reviewing the statement of work (SOW), two stakeholders disagree on what the project...
- Q107. A project to deliver financial and administrative changes related to taxation regulations ...
- Q108. Keeping up with the growth was becoming a problem for a privately owned Chinese financial ...
- Q109. The project scope statement and resource calendars are inputs to which Project Time Manage...
- Q110. The process of monitoring the status of the project and product scope as well as managing ...
- Q111. Scope, schedule, and cost parameters are integrated in the:...
- Q112. The outcome that must be produced to complete a part of a project or the project itself is...
- Q113. What tool and technique is used to determine whether work and deliverables meet requiremen...
- Q114. To account for uncertainty in a schedule, reserve analysis may be used. All the following ...
- Q115. You are constructing a probability and impact matrix for your project. Which of the follow...
- Q116. When choosing the most appropriate form of project organization, the first step is to_____...
- Q117. A complex project is in the execution phase. A key stakeholder who is new to the project h...
- Q118. While preparing for project hand-over to the operations team, the project manager discover...
- Q119. A key stakeholder is concerned about a critical risk that may cause the project to run ove...
- Q120. Which of the following response strategies are appropriate for negative risks or threats?...
- Q121. A project manager is assigned to a digital transformation project for a bank. The company ...
- Q122. A project is being delayed due to a large amount of rework caused by a quality problem tha...
- Q123. Written change requests should be required on______________...
- Q124. A project manager joins a project to handle the merger between a digital marketing firm an...
- Q125. A company has assigned a project manager to the initial task of determining the resources ...
- Q126. Which provides the basic framework for managing a project?...
- Q127. If you are calculating one early start and early finish for each task, you are using: (cho...
- Q128. Assume you are working as the project manager on the first project in your company to use ...
- Q129. Which of the following is best for handling cross functional project needs for a large, co...
- Q130. Which of the following statements regarding WBS are FALSE?...
- Q131. Midway through a project in a matrix organization, the project manager discovers a resourc...
- Q132. Which of the following is NOT a valid reason to authorize a project?...
- Q133. Who is responsible for determining which processes from the Process Groups will be employe...
- Q134. The purpose of inspection in Perform Quality Control is to keep errors:...
- Q135. After a meeting with the customer, the project manager receives special recognition becaus...
- Q136. The team implemented a risk response plan when a vendor was unable to fulfill a contract c...
- Q137. Which of the following statements are FALSE regarding the Resource Calendar?...
- Q138. An output of the Create WBS process is:
- Q139. Which of the following is a means of reaching a group decision in which everyone agrees on...
- Q140. A project manager is assigned to an ongoing project and receives notification from another...
- Q141. A construction services company has influence within the local community with the potentia...
- Q142. Which tool or technique is effective in a project in which the deliverable is not a servic...
- Q143. During a project status update by the project management office (PMO), the CEO is concerne...
- Q144. Power, urgency, and legitimacy are attributes of which stakeholder classification model?...
- Q145. A project manager, leading a new project at a large corporation, must develop a high-level...
- Q146. A project manager is acting as a servant leader and is struggling to make deadlines on a c...
- Q147. You are the project manager for a construction company that is building a new city and cou...
- Q148. During the implementation phase of a construction project, a key supplier went bankrupt an...
- Q149. A third-party supplier demands payment for the services provided for a project. The agreem...
- Q150. In which phase of team building activities do team members begin to work together and adju...
- Q151. Your project has been under way for some time, but indicators show that it is in trouble. ...
- Q152. A project manager is working on a multiphase networking project. Phase 1 is scheduled to f...
- Q153. Who has MOST of the power in projectized organization?...
- Q154. Increased attention to return on investment (ROI) now requires you to complete a financial...
- Q155. To which process is work performance information an input?...
- Q156. The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (...
- Q157. Project documentation includes a few assumptions considered during the early stages of the...
- Q158. An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a ...
- Q159. A project's budgeted value of work completed is less than the authorized budget for planne...
- Q160. In a matrix organization, which of the following is not a responsibility of the project ma...
- Q161. The team is involved in defining what is needed to ensure that the quality process will ca...
- Q162. The simplest form of quantitative risk analysis and modeling techniques is______________...
- Q163. A project manager notices that a vendor consistently revises deliverables that provide inp...
- Q164. Which of the following is an example of a technique used in quantitative risk analysis?...
- Q165. The retail chain will be using a vendor to provide engineers for a security camera network...
- Q166. Which of the following is a tool or technique used in the Determine Budget process?...
- Q167. During a meeting to define project scope a stakeholder tells the project manager that the ...
- Q168. A project manager has just taken over a project that is in the requirements gathering phas...
- Q169. Which schedule method allows the project team to place buffers on the project schedule pat...
- Q170. Which of the following statements are true regarding proposals EXCEPT:...
- Q171. Which of the following is the MOST valuable result of creating the work breakdown structur...
- Q172. The project manager has learned that the project sponsor is unhappy with the development o...
- Q173. A project lifecycle is defined as:
- Q174. Which of the following forecasting methods uses historical data as the basis for estimatin...
- Q175. All are the part of scope baseline except:
- Q176. In the middle of a project, it becomes clear to the project manager that the project's ben...
- Q177. During a review meeting, the project manager realizes that scheduled quality control inspe...
- Q178. The run chart created during the Perform Quality Control process on a project is used to s...
- Q179. What tool have project managers come to use to identify all of the costs associated with a...
- Q180. Which is not part of the Earned Value calculations?...
- Q181. You are the project manager at a utility company. Due to the recent rise in the cost of pe...
- Q182. A project's planning phase has just been completed and was defined by team members in remo...
- Q183. A project manager finds out that the required project status reports have not been filled ...
- Q184. As the project progresses, which of the following is routinely collected from the project ...
- Q185. Which of the following process groups are in loop back relationship with the other, where ...
- Q186. A structured review of the seller's progress to deliver project scope and quality within c...
- Q187. Inputs to contract administration do not include:...
- Q188. Which type of team can be defined as a group of people with a shared goal who fulfill thei...
- Q189. A project team is working on an agile software development project. The project manager is...
- Q190. One way to make it more likely practice project risk management on projects is to_________...
- Q191. Forcing, as a means to manage conflict:
- Q192. Communication plays a major role in:
- Q193. The process of monitoring specific project results to determine if they comply with releva...
- Q194. To increase the likelihood of project success, project manager A interviews project manage...
- Q195. Which of the following describes an input to the direct and manage project execution proce...
- Q196. In the Plan Stakeholder Management process, expert judgment is used to:...
- Q197. An agile project manager would like to convert the requirements document into epics, capab...
- Q198. Which of the following is true regarding NPV?
- Q199. The scope management plan is a subsidiary of which project document?...
- Q200. Analogous cost estimating relies on which of the following techniques?...
- Q201. Before authorizing resource assignments, a company's project management office (PMO) requi...
- Q202. Integrated change control includes the following activities EXCEPT:...
- Q203. Every project creates a unique product, service, or result that may be:...
- Q204. What's budget?
- Q205. A project manager is working on a highly complex project. During the execution of the proj...
- Q206. To practice effective schedule control, your project team must be alert to any issues that...
- Q207. During the execution of a project the project manager notices that only one team member ha...
- Q208. There has been a change to the scope of your project, which may adversely impact the proje...
- Q209. Since risk is associated with most projects, the best course of action is to:...
- Q210. The person assigned by the performing organization to be responsible for achieving the pro...
- Q211. The ability to influence cost is greatest during which stages of the project?...
- Q212. Which of the following is not a type of performance reporting:...
- Q213. The reason that the cost performance index (CPI) is shown as a ratio is to______________...
- Q214. Which of the following types of cost are relevant to making financial decisions:...
- Q215. To make an informed decision about buying insurance, the project manager needs to determin...
- Q216. The project team is experiencing schedule delays due to issues arising with suppliers. Som...
- Q217. While developing the project charter, stakeholders disagree about the projects most import...
- Q218. You are trying to determine whether or not to conduct 100% final system tests of 500 groun...
- Q219. Project managers for international projects should recognize key issues in cross-cultural ...
- Q220. After preparing the work breakdown structure (WBS), the project manager is ready to assign...
- Q221. Prioritizing risks for further analysis or action by assessing and combining their probabi...
- Q222. You are the project manger at a leading manufacturer of consumer electronics, personal com...
- Q223. As project manager, you have assembled the team to prepare a comprehensive list of project...
- Q224. Design of experiments (DOE) should be used during which of the following processes?...
- Q225. A project manager and project learn have successfully implemented a new product line at th...
- Q226. After completion of a project's first deliverable, a stakeholder advises that it does not ...
- Q227. Changes to formally controlled documentation, plans, etc. to reflect modified or additiona...
- Q228. Which tool or technique is required in order to determine the project budget?...
- Q229. A project manager is planning a project that has 40 stakeholders. The project manager deci...
- Q230. After receiving the hardware components from a vendor that will be used later in the proje...
- Q231. During a project's execution phase. the project manager receives notice from environment a...
- Q232. A local company is developing a new product and, for the first time, using a remote team f...
- Q233. Changes in the report formats and lessons learned documents process should trigger changes...
- Q234. A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went...
- Q235. The following is a network diagram for a project. (Exhibit) The shortest non-critical path...
- Q236. When writing the roles and responsibilities of your team members, you should document the ...
- Q237. vendor informed the project manager that a critical resource will be on a long leave of ab...
- Q238. Which is a phased budget used to measure and monitor cost performance on the project?...
- Q239. Which of the following describes the difference between the maximum funding and the end of...
- Q240. A project manage identifies the root cause of a quality issue and implements corrective ac...
- Q241. A risk that arises as a direct result of implementing a risk response is called a:...
- Q242. The team for a large software implementation project believes that the project is on track...
- Q243. A full-time project manager with low to moderate authority and part-time administrative st...
- Q244. Expert judgment is a tool/ technique in all of the following EXCEPT:...
- Q245. The stakeholder register is an output of:
- Q246. In a complex project with several subcontractors, one subcontractor reports a likely delay...
- Q247. You have just joined a new organization as a project manager. The new organization has a p...
- Q248. As a result of a new investor's participation stakeholders receive status reports and proj...
- Q249. Exhibit A is an example of which of the following types of Sequence Activities? (Exhibit)...
- Q250. A project manager asks the team to provide an evaluation of the project's contingency plan...
- Q251. A SPI < 1 indicates which of the following?...
- Q252. What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the ac...
- Q253. A project manager receives a request for proposal (RFP) and must respond to the estimation...
- Q254. Which of the following is or are a part of Solicitation process...
- Q255. Your project schedule has slipped by 2 weeks, and you have to take corrective action to br...
- Q256. A project manager is finalizing the stakeholder engagement plan. The project manager refer...
- Q257. All of the following can be used in lieu of the term "bidders conferences" EXCEPT ________...
- Q258. A new solution is being deployed in countries A B and C. This solution will allow the coun...
- Q259. Enterprise environmental factors are an input to which process?...
- Q260. You are a personnel management specialist recently assigned to a project team working on a...
- Q261. A project manager decided to use a highly adaptive approach to manage a large-scale projec...
- Q262. Which of the following tools and techniques can be used to collect information for the pro...
- Q263. A car manufacturing company wants to develop an unmanned car as a new product. A project m...
- Q264. During a sprint, one of the team members found an issue. According to the team member and ...
- Q265. You are managing a design project that would provide design drawings to your customer. The...
- Q266. Projects are separated into phases or subprojects; these phases include:...
- Q267. The city has decided to build a new tram station The project will include various approach...
- Q268. You are in process of analyzing the effects of identified risks. Which of the following is...
- Q269. A project manager is working on a project that is using a hybrid approach. One key input f...
- Q270. During the project initiation phase, the project manager is identifying key deliverables b...
- Q271. Schedule milestones and a predefined budget are examples of:...
- Q272. A project team began working on a complex project that involves new technology as a produc...
- Q273. The item that provides more detailed descriptions of the components in the work breakdown ...
- Q274. All of the following should be included in the initial staffing management plan as part of...
- Q275. The outputs of Contract Administration are correspondence, contract changes, and payment r...
- Q276. The business manager and the product owner are requesting a more flexible way to incorpora...
- Q277. If you apply the configuration management system along with change control processes proje...
- Q278. Within a matrix organization, dual reporting of team members is a risk for project success...
- Q279. You work for a telecommunications company, and when developing a project management plan f...
- Q280. Estimated at Completion is determined by:
- Q281. Specification of both the deliverables and the processes is the focus of:...
- Q282. Characteristics of project phases are:
- Q283. Which of the following processes is involved with allocating the overall cost estimate to ...
- Q284. Write preparing a projects third progress report, the project manager identifies that the ...
- Q285. Scheduling is the process by which decisions are made concerning:...
- Q286. The Verify Scope process is primarily concerned with:...
- Q287. A project manager is assigned a US multimillion-dollar protect During execution, me projec...
- Q288. What is one of the objectives of Project Risk Management?...
- Q289. A recently appointed project manager is in constant conflict with a senior manager Since t...
- Q290. All the following are project baselines that are generally part of the project management ...
- Q291. A project manager is managing a hybrid project. After attending an iteration review, a sta...
- Q292. During which process would stakeholders provide formal acceptance of the completed project...
- Q293. Resource reallocation from non critical to critical activities is an example of which Proj...
- Q294. Which technique is commonly used for the Perform Quantitative Risk Analysis process?...
- Q295. The difference between the BCWS and the BCWP is referred to as the:...
- Q296. A project manager was recently assigned to a project that is in the execution phase and is...
- Q297. A client adds a new feature and requests a budget update the development of this feature c...
- Q298. Quality inspections also may be called______________...
- Q299. A project manager is assigned to a project in a company that is transitioning to agile Not...
- Q300. A project manager who is new to an organization observes that an approaching deadline is l...
- Q301. A project manager should communicate to stakeholders about resolved project issues by upda...
- Q302. All the following statements related to Benefit Cost Ratio (BCR) are correct Except:...
- Q303. Procurement audits, negotiated settlements, and a records management system are tools and ...
- Q304. You are the project manager at a utility company. Due to the recent rise in the cost of pe...
- Q305. Who is responsible for initiating a project?
- Q306. You are a project manager working on a project when the customer wants another feature add...
- Q307. A comparison of completion status to baseline is referred to as _____....
- Q308. Very late into project execution, the project manager realizes that the materials supplier...
- Q309. The project scope statement addresses and documents all the following items EXCEPT________...
- Q310. Characteristics of a code of accounts are
- Q311. A new government regulation has mandated that all team members will need to work remotely ...
- Q312. Activities with zero time duration are referred to as:...
- Q313. The following is a network diagram for a project. (Exhibit) The total float for the projec...
- Q314. By the end of the first sprint, a project lead notices that one of the team members is not...
- Q315. An IT project manager has been referred to a new, highly rated vendor that provides qualit...
- Q316. You are the project manager for a top-secret software project for an agency of the United ...
- Q317. A project manager has finished the project. He knows that the project scope has been compl...
- Q318. The project is in a projectized environment. There are significant challenges with meeting...
- Q319. During the planning phase of a project, the project manager learns that the sponsor has el...
- Q320. When closing a project or phase, part of the process may require the use of which type of ...
- Q321. In a time-critical construction project, a misunderstanding occurred between the superviso...
- Q322. The performance measurement baseline consists of all the following EXCEPT______________...
- Q323. The Project Manager is involved in acquiring the project team on a highway expansion proje...
- Q324. A Project Manager has been working on quality process of a project at a major defense cont...
- Q325. The process of identifying and documenting relationships among the project activities is k...
- Q326. Cost of quality (COQ) refers to total cost of/to:...
- Q327. The product scope description is used to:
- Q328. Sharing good practices introduced or implemented in similar projects in the organization a...
- Q329. During a retrospective meeting, the project team discussed the high rate of defects during...
- Q330. Provisional training is provided for a project that is in the process of client hand-over....
- Q331. A new project manager on a project with a very tight budget is struggling, as they have no...
- Q332. Who, along with the project manager, is supposed to direct the performance of the planned ...
- Q333. What is not true for project deliverables?
- Q334. Which of the following describes tool/ technique where expenditure of funds is reconciled ...
- Q335. Which is not one of the five classifications of work found in a purchasing operafion?...
- Q336. Team building should be ongoing throughout the project life cycle. However, it is hard to ...
- Q337. While inspecting a contractor's progress, the project manager notices that the contractor ...
- Q338. During project monitoring, the project manager learns of a small gap between the quality o...
- Q339. Which of the following statements are FALSE regarding the critical chain method?...
- Q340. The purpose of inspection in Perform Quality Control is to keep errors:...
- Q341. (Exhibit) An agile team has sized all of the features for the release. Using the table abo...
- Q342. An IT department's deliverable is two weeks late. If the deliverable is not completed by t...
- Q343. Which of the following types of specifications gives measurable capabilities of the produc...
- Q344. Risk exists the moment that a project is:
- Q345. Which of the following calculates how much additional budget is required in order to compl...
- Q346. Which of the following is an output of Close Procurements?...
- Q347. During the execution of an IT project, a project manager warns of the possibility that the...
- Q348. When large or complex projects are separated into distinct phases or subprojects, all of t...
- Q349. You've constructed the WBS for your recent project. You've requested that the subproject m...
- Q350. Which of the following will provide the basis for estimating, scheduling, executing, and m...
- Q351. Root Cause Analysis related to ________.
- Q352. A multinational company with a cross-border project wants to implement new software that w...
- Q353. The project charter is an input to which process?...
- Q354. While reviewing a project management plan for approval, one of the key stakeholders states...
- Q355. As you manage the railroad switching station project, you are concerned that the business ...
- Q356. Coordinating changes across knowledge areas is a function of:...
- Q357. The major difference between the project coordinator and project expeditor forms...
- Q358. Project Managers have least power in which organization structure...
- Q359. A project manager for a large software delivery project is in the process of finalizing th...
- Q360. During a project's next phase, an architect will take a three-month maternity leave. What ...
- Q361. Identify Stakeholders is the process of identifying all of the people or organizations imp...
- Q362. Which can be used to determine whether a process is stable or has predictable performance?...
- Q363. A project team is performing a post-release evaluation of a product that requires detailed...
- Q364. The key benefit of the Monitoring and Controlling Process Group is the ability to:...
- Q365. A stakeholder informs the project manager that they do not receive the weekly project stat...
- Q366. A project manager is managing a project that is halfway through its execution phase and th...
- Q367. During the execution of a project to build a complex defence system, your team has run int...
- Q368. A complex system is being replaced and detailed requirements have just been completed. Whi...
- Q369. Plan Risk Management is the process of defining how to:...
- Q370. During regular project progress review meetings, one team member shares bad news that has ...
- Q371. The marketing team is transitioning to using hybrid approaches for their projects. The mar...
- Q372. Drag and Drop Question Drag the communication event on the left to the main subject discus...
- Q373. A project manager is worried that a key stakeholder is not participating in the project an...
- Q374. Statistical cost estimating techniques (based upon history), are called _____ estimates an...
- Q375. The progressive detailing of the project management plan is called:...
- Q376. A project manager notices that there is limited participation and contribution from a new ...
- Q377. A project manager has been assigned to a project where collaboration with the business is ...
- Q378. A project manager is working on a large project in another country and realizes that only ...
- Q379. What can a project manager do to communicate the formal project announcement and relevant ...
- Q380. During the development of a project in a dynamic market environment, new unforeseen legal ...
- Q381. You are the project manger at an advertising firm that specializes in marketing and promot...
- Q382. A project that is using an incremental approach has colocated team members and is using a ...
- Q383. On a virtual project team, there is a team member who consistently has issues with the tec...
- Q384. A project manager is working on an agile project that is within the scope of a recently an...
- Q385. You are the project manager at Happy Coffee Cafe, a rapidly growing franchise selling prem...
- Q386. A project manager is leading project teams across various countries and time zones. When d...
- Q387. The data warehouse project is about halfway complete at a major retail client. Your compan...
- Q388. You are a project manager at a project company developing wireless mobile applications. Yo...
- Q389. In a hybrid project, 100 new base stations are being added to a 4G mobile network every mo...
- Q390. A project manager is managing a project that is operating in a remote, international locat...
- Q391. Despite the project manager's continual reminders about the project's scope, a stakeholder...
- Q392. A company attorney, newly hired by the company, walks into the project manager's office an...
- Q393. A key stakeholder believes that the project manager fails to have the authority level nece...
- Q394. All of the following statements regarding bidder conferences are true EXCEPT:...
- Q395. A project's primary focus is staying on schedule. To monitor this, the project manager req...
- Q396. You are in the process of developing an approved project schedule that will serve baseline...
- Q397. The risk management team of a software project has decided that due to the lack of adequat...
- Q398. What is one of the MAJOR outputs of activity sequencing?...
- Q399. Exhibit: (Exhibit) According to the information in the grid, what is the estimate at compl...
- Q400. A project has been initiated that has several project stakeholders from various department...
- Q401. During the planning stage of a project, a project manager identifies many risks that could...
- Q402. A new project manager is planning an information security project for a company that resid...
- Q403. Which of the following BEST describes the procedures by which the project schedule can cha...
- Q404. Management has grown weary of the many surprises, mostly negative, that occur on your proj...
- Q405. The Project Manager has scheduled weekly status meetings with the team. The meetings have ...
- Q406. During the closing process, the project manager learns that one deliverable is not meeting...
- Q407. Which type of analysis is used to determine the cause and degree of difference between the...
- Q408. A project has critical time and budget constraints. An important resource responsible for ...
- Q409. A company has to make a choice between two projects, because the available resources in mo...
- Q410. Which of the following Process Groups covers all Project Management Knowledge Areas?...
- Q411. A team has been struggling with various issues during the course of an iteration. The proj...
- Q412. In a weekly status meeting with the client, the project manager asks each team member to p...
- Q413. A project manager is managing a transformation project that is already in the execution ph...
- Q414. You are using earned value progress reporting for your current project in an effort to tea...
- Q415. The client will not agree to closure, claiming that the project team has not performed the...
- Q416. Which of the following is a statistical concept that calculates the average outcome when t...
- Q417. Which stakeholder classification model groups stakeholders based on their level of authori...
- Q418. A project manager is working on a large project with a very difficult client. During the c...
- Q419. The sending or conveying of information from one place to another is the process of...
- Q420. In project management, a temporary project can be:...
- Q421. Due to stakeholders' schedule commitments an expansion project is being fast tracked Some ...
- Q422. A company is making a decision regarding which model of equipment to buy for its next proj...
- Q423. Which of the following are inputs into the Administer Procurements process?...
- Q424. The earned value report BCWP at the end of the project...
- Q425. While working on a project, the project manager realizes that stakeholders' delivery expec...
- Q426. The process of estimating the type and quantity of material, human resources, equipment, o...
- Q427. You are a project manager of ABC organization. Your project covers more than one departmen...
- Q428. During what phase of project lifecycle is the level of risk and uncertainty is the lowest?...
- Q429. The acquisition of project team members is dependent upon the performance of the human res...
- Q430. The contract type that often spans multiple years and allows for final adjustments to the ...
- Q431. You have now prepared your cost management plan so now you are preparing your project's co...
- Q432. Drag and Drop Question An experienced project manager is overseeing a merger and acquisiti...
- Q433. A project manager identifies the root cause of a quality issue and implements corrective a...
- Q434. A team member misses a project meeting without it being approved and has been penalized as...
- Q435. A company is transitioning projects from a predictive to an agile approach. The CFO is con...
- Q436. Which of the following statements are true regarding the critical path of a project schedu...
- Q437. A proof of concept for a proposed solution was conducted during the project implementation...
- Q438. Which tool or technique is used to manage change requests and the resulting decisions?...
- Q439. During project planning, the project manager wants to transfer as many cost overrun risks ...
- Q440. You are managing the development of a highly controversial project. Today you called a tea...
- Q441. Which of the following terms indicates a deliverable-oriented hierarchical decomposition o...
- Q442. The individual or group that provides resources and support for a project and is accountab...
- Q443. The end point of a project phase can be referred to as:...
- Q444. All of the following are examples of quality metrics EXCEPT:...
- Q445. You plan to issue a purchase order (PO) to a supplier to provide services to the project. ...
- Q446. The process improvement plan details the steps for analyzing processes to identify activit...
- Q447. Which of the following is an output from Control Scope?...
- Q448. During a project gate review meeting, it is identified that one of the project deliverable...
- Q449. Which of the following tools and techniques is used in the Develop Project Team process?...
- Q450. In a housing project, the real estate developer and the building contractor disagree about...
- Q451. Which of the following correctly describes when organizations and stakeholders are willing...
- Q452. A technology project is delivering new functionality on a new platform. Several team resou...
- Q453. Resource calendars are included in the:
- Q454. The processes required to establish the scope of the project, refine the objectives, and d...
- Q455. You have been hired as a project manager for a local bank. Bank wants to develop and desig...
- Q456. Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days....
- Q457. A key import supply has suffered a delay of 6 months. The delay affects a functionality th...
- Q458. During a weekly status meeting, a team member informs the project manager that the design ...
- Q459. A project manager is working on a project for a startup company. The company launched clou...
- Q460. You have been assigned to a project that will allow job seekers to fill out applications a...
- Q461. A project manager is managing an innovation project for a big corporation. The project man...
- Q462. Alter the root cause of defective deliverables is identified, the project director decides...
- Q463. The business needs, assumptions, and constraints and the understanding of the customers ne...
- Q464. In the Define Activities process, the schedule management plan is used to:...
- Q465. You are collecting information regarding project progress and project accomplishments and ...
- Q466. A person is writing a document identifying the business need for a project and is includin...
- Q467. A project stakeholder requested a scope enhancement that was not approved due to budget co...
- Q468. The sponsor of a project requests to see a prototype for a project deliverable Three optio...
- Q469. A project manager who is new to a matrix organization has just been assigned to an interna...
- Q470. What is one of the objectives of Project Risk Management?...
- Q471. A key benefit of the Manage Communications process is that it enables:...
- Q472. In your project, you are trying to identify lessons learned that can improve performance o...
- Q473. A project team is struggling to obtain the required data for a complex project in order to...
- Q474. According to Maslow's hierarchy of needs in which does the need for acceptance occurs?...
- Q475. A key to successful Management by Objectives (MBO) is...
- Q476. A protect manager is struggling 10 obtain participation from key stakeholders who do not u...
- Q477. A project manager who takes over halfway through a project determines that the cost perfor...
- Q478. A project manager is reviewing the status of a large project with team members in differen...
- Q479. What are the five Project Management Process Groups?...
- Q480. A project team member complained to the project manager that they are not sure if they are...
- Q481. While developing the cost management plan, the project manager discovers that the budget n...
- Q482. Typical outcomes of a project include:
- Q483. A distributed protect team wants to use the common ground principle to ensure that they ha...
- Q484. While managing a project using a hybrid approach, the project manager realizes that there ...
- Q485. Project managers must know:
- Q486. A project's business case was just approved and the project manager is creating the benefi...
- Q487. Which stakeholder classification model groups stakeholders based on their level of authori...
- Q488. The Perform Integrated Change Control process occurs in which Process Group?...
- Q489. You are a Project Manager, and you want your team to use (WBS) in cost estimation develope...
- Q490. Earned value analysis is a performance reporting tool/ technique used in manage stakeholde...
- Q491. During project initiation, the project manager teams that the charter was not approved by ...
- Q492. Which of the following strategies is used to deal with risks that may have a negative impa...
- Q493. Portfolio Management is management of:
- Q494. A project manager has expertise in the technical domain. The project manager frequently de...
- Q495. Which of the following organization holds the project manager's authority the weakest...
- Q496. Douglas McGregor's Theory Y advocates that the average worker:...
- Q497. The baseline for evaluating whether requests for changes or additional work are contained ...
- Q498. Which tools or techniques are used during the Close Project or Phase process?...
- Q499. During the execution of a US$20 million project in a balanced matrix structure, a subject ...
- Q500. The first step in collecting requirements on any project, large or small, is to___________...
- Q501. A team member who is working on a critical project deliverable reported that their compute...
- Q502. A project manager is starting a project using a hybrid approach and notices some team memb...
- Q503. A project is scheduled to end in 2 weeks. The team is expected to continue working long ho...
- Q504. Activity resource requirements and the resource breakdown structure (RBS) are outputs of w...
- Q505. An iteration is almost finished, but the team is struggling to complete the stories that r...
- Q506. You are using tools and techniques of the Collect Requirements process. You are visually d...
- Q507. During a bidders conference, it is important that______________...
- Q508. Company A recently signed a contract with a vendor to supply an engineering service. The p...
- Q509. A project manager has been assigned to lead a major project in a government organization. ...
- Q510. During the implementation phase of a construction project, a key supplier went bankrupt an...
- Q511. Screening of risk events for potential risk is known as _____ ....
- Q512. Project A has a NPV of $275K US over 2.5 years. Project B has an IRR of 3.2%. Project C ha...
- Q513. During a project's planning session, the project team discussed selecting the required inf...
- Q514. A project manager has been assigned to deliver a challenging project on time and within bu...
- Q515. You are a fabulous project manager, and your team thinks highly of you. You are well respe...
- Q516. When a permitting agency takes longer than planned to issue a permit, this can be describe...
- Q517. You are a project manager for a software project. Various tools and techniques determine p...
- Q518. Some company board of director members feel that the organization does not prossess the ca...
- Q519. The project manager for XYZ stationers is sequencing the activities for the project to set...
- Q520. Which of the following is an example of contract administration?...
- Q521. A project manager is leading a regulatory project that involves multiple geographic locati...
- Q522. The process that translates the quality management plan into executable quality activities...
- Q523. During a regular review, the project manager of an agile project realizes that a key stake...
- Q524. The project is nearing completion. The team is involved in a lot of different activities t...
- Q525. Project selection criteria cover management concerns such as:...
- Q526. The company is implementing a new project management approach. In the past, their projects...
- Q527. A project manager is leading a project with several stakeholders in other functional areas...
- Q528. You are the project manger at a software company developing the next-gen web application s...
- Q529. The total project scope is:
- Q530. The project charter is an input to which process?...
- Q531. The sponsor is conducting a meeting and a Project Manager is reporting that his project is...
- Q532. The actual configuration of a PERT/CPM network _____ the amount of resources that can be d...
- Q533. Which is the BEST description of project scope?...
- Q534. A company just started managing a project using an agile approach Due to this change the g...
- Q535. While reviewing a status report a project manager notices that over a period of six months...
- Q536. Which of the following change requests can bring expected future performance of the projec...
- Q537. When addressing roles and responsibilities,which item ensures that the staff has the skill...
- Q538. When a control chart is used to monitor performance of a process, which of the following w...
- Q539. According to a new product development process, the marketing department will begin adding...
- Q540. The following chart contains information about the tasks in a project. (Exhibit) Based on ...
- Q541. During the execution phase of a project, one of the customer's stakeholders keeps requesti...
- Q542. During a sprint review, the product owner expresses concerns that, due to changes since th...
- Q543. A team is ready to start working on a project with a customer who was very difficult to wo...
- Q544. Which term describes those costs in a contract that are associated with two or more projec...
- Q545. During an audit, it was noted that only 20 percent of completed projects had documented le...
- Q546. A project's cost performance index (CPI) and schedule performance index (SPI) are both gre...
- Q547. Administer Procurements is part of which Process Group?...
- Q548. A project manager invites the new CIO to a meeting to review a project's key deliverables,...
- Q549. Which action should a project manager take to ensure that the project management plan is e...
- Q550. Micheal is a self employed PMP certified project manager who is currently working as a con...
- Q551. An output of the Manage Stakeholder Engagement process is:...
- Q552. In which of the following contract types does the buyer have the most cost risk?...
- Q553. Examples of team building activities include:
- Q554. The customer has reviewed the deliverables of a project and finds that they are acceptable...
- Q555. In a hybrid project a stakeholder requests some feature modifications directly to one of t...
- Q556. Quality is:
- Q557. The following chart contains information about the tasks in a project. (Exhibit) Based on ...
- Q558. A project manager conducts an inquiry into the increase of scrapped material over the past...
- Q559. In a hybrid project, the customer has issued a contract that specifies the deliverables fo...
- Q560. Which of the following terms indicates a deliverable-oriented hierarchical decomposition o...
- Q561. Since you are in the preliminary stages of your project, you estimate that your project wi...
- Q562. A project manager Is working on the initial phases of a highly technical project that empl...
- Q563. Which process involves subdividing project deliverables and project work into smaller, mor...
- Q564. You are in the process of defining the specific activities that need to be performed to de...
- Q565. This process uses tools like decomposition and rolling-wave planning to produce the activi...
- Q566. During an ongoing project, the customer requests that new requirements be delivered withou...
- Q567. You are working on a warehouse project when you realize that you may miss the due date of ...
- Q568. A project manager has received a new request to integrate more features to a product. The ...
- Q569. The core function of the PM is
- Q570. Which of the following is contained within the communications management plan?...
- Q571. Which group creativity technique asks a selected group of experts to answer questionnaires...
- Q572. An input to the Plan Stakeholder Management process is:...
- Q573. Which tool or technique is used in Close Procurements?...
- Q574. Which of the following is an output of the Plan Quality process?...
- Q575. A project manager is using a subcontractor for mobile application development. When the pr...
- Q576. Which of these types of matrix structure gives the project manager the most control?...
- Q577. A company announces that is corporate strategy has changed and it will be necessary to clo...
- Q578. Which is not an input to Procurement Planning?...
- Q579. Cost of quality (COQ) refers to total cost of/to:...
- Q580. Based on the following table, what are the total float and free float for activity (H)? (E...
- Q581. During the first project meeting with a new project manager, a stakeholder complains about...
- Q582. At the start of a typical project life cycle, costs are:...
- Q583. A project is in the middle of the fifth iteration. Due to a sudden slump in the economy, t...
- Q584. Outputs from the Initiation process include:
- Q585. All of the following are elements of inputs of the Risk Identification process that you sh...
- Q586. In the Define Activities process, the schedule management plan is used to:...
