Why is the 'initiating a project' process used?
Correct Answer: B
Reference https://www.whatisprince2.net/prince2-process-initiating-a-project.php
Add Comments
- Other Question (233q)
- Q1. Why is the 'initiating a project' process used?...
- Q2. Which is NOT obtained from a product's Product Description?...
- Q3. Which theme verifies that a project's products are fit for purpose?...
- Q4. In what product should the quality criteria for a specialist product be recorded?...
- Q5. Which project management team member represents the interest of those who will operate the...
- Q6. What is performed as part of the recommended risk management procedure?...
- Q7. Which of the following are objectives of the Directing a Project process? 1 . Ensure corpo...
- Q8. When should the level of tailoring be defined?...
- Q9. During the 'initiating a project' process, who specifies the required level of management ...
- Q10. Which is the base product against which the Project Board can assess progress, issues and ...
- Q11. According to PRINCE2, why might there be more than one business case for a project?...
- Q12. Which statement about risks is FALSE?
- Q13. Which process ensures focus on the delivery of a stage's products and avoids uncontrolled ...
- Q14. Identify the missing words in the following sentence. A project is [ ? ] organization that...
- Q15. Which risk response type is appropriate to respond to an opportunity?...
- Q16. What is an off-specification?
- Q17. How should the Team Manager report that tolerances are forecast to be exceeded?...
- Q18. Which is a purpose of the Directing a Project process?...
- Q19. What should the 'managing product delivery' process ensure? 1. That the planned products m...
- Q20. Which statement about stages is true?
- Q21. Which statement applies to Stage Plans?
- Q22. Which of the following can be done to control the size of the Project Board on a project t...
- Q23. Which process is triggered towards the end of the final stage when all the assigned work h...
- Q24. According to the 'defined roles and responsibilities' principle, how many categories of st...
- Q25. Which theme provides all management levels within the project management team with mechani...
- Q26. Who does the Team Manager report to and take direction from?...
- Q27. As a minimum requirement for applying the risk theme, what must specifically be assessed?...
- Q28. Identify the missing words in the following sentence. The role of [ ? ] is assigned to the...
- Q29. Which level of management sets the project level tolerances?...
- Q30. Which role is responsible for ensuring the project is justified in terms of cost?...
- Q31. Which is a purpose of the Initiating a Project process?...
- Q32. Which is one of the six aspects of project performance that needs to be managed?...
- Q33. Which is a FALSE statement about technical stages?...
- Q34. Which statement is FALSE?
- Q35. Which describes an off-specification?
- Q36. What must be produced to meet the minimum requirements for applying the change theme?...
- Q37. Which of the following is NOT an event-driven control?...
- Q38. According to the 'defined roles and responsibilities' principle, what must be represented ...
- Q39. What is the minimum number of management stages required by PRINCE2?...
- Q40. Which is a minimum requirement for applying the plans theme?...
- Q41. If the Project Board instructs the Project Manager to implement a request for change, whic...
- Q42. Which PRINCE2 principle is being applied when tolerances are set for the three levels of p...
- Q43. According to the 'continued business justification' principle, when is a justifiable reaso...
- Q44. Which is a purpose of the Quality theme?
- Q45. Which is a factor when deciding the duration of a management stage?...
- Q46. Which is a minimum requirement for applying the risk theme?...
- Q47. Which statement applies to Stage Plans?
- Q48. Which is an objective of the Managing Product Delivery process?...
- Q49. Which is part of quality control?
- Q50. What product defines the reporting requirements between the Project Manager and Team Manag...
- Q51. Which statement about the Directing a Project process is true?...
- Q52. Which is a purpose of the Managing a Stage Boundary process?...
- Q53. Which level of management uses the mechanisms established by the Progress theme to control...
- Q54. What process aims to ensure accurate progress information is provided to the Project Manag...
- Q55. Which is the base product against which the Project Board can assess progress, issues and ...
- Q56. Which is part of quality control?
- Q57. Which is NOT one of the PRINCE2 integrated elements?...
- Q58. Identify the missing word(s) in the following sentence. The Quality theme provides a set o...
- Q59. Which is the Change Authority role permitted to authorize?...
- Q60. What is the collective name for individuals or groups who may be affected by a project?...
- Q61. Which role is part of the project management team?...
- Q62. What must be produced to meet the minimum requirements for applying the change theme?...
- Q63. Which process monitors work that has been assigned to a team manager?...
- Q64. What is a benefits management approach used to assess?...
- Q65. Which principle helps to ensure that all changes to the outputs are agreed?...
- Q66. Which aspect of project performance must be managed to avoid misunderstandings on what the...
- Q67. Which statement is true for ALL project stakeholders?...
- Q68. What is described as an organization's unique attitude towards risk taking...
- Q69. In which product does a Project Manager define the time and cost tolerances for the work t...
- Q70. Which is a purpose of the Organization theme?
- Q71. Which theme provides all management levels within the project management team with mechani...
- Q72. Which is NOT a purpose of a Benefits Review Plan?...
- Q73. Which is created during the Starting up a Project process?...
- Q74. Which may be funded from a risk budget?
- Q75. Which is a purpose of the 'closing a project' process?...
- Q76. Which is a purpose of the Directing a Project process?...
- Q77. Which should be provided by a project mandate?...
- Q78. Which principle helps to define what should be included and what should be excluded from a...
- Q79. Which is a purpose of the Managing a Stage Boundary process?...
- Q80. What plan is created, and submitted for approval, during the Managing a Stage Boundary pro...
- Q81. If a project is part of a programme, which 'starting up a project' process activities are ...
- Q82. Which is a purpose of the Starting up a Project process?...
- Q83. Which should be provided by a project mandate?...
- Q84. What must be done for a project to be a PRINCE2 project?...
- Q85. Which is an objective of the Directing a Project process?...
- Q86. Which is NOT considered when defining risk tolerance?...
- Q87. Which does NOT reflect the PRINCE2 principle of continued business justification?...
- Q88. Which product is created in the 'starting up a project' process to define and confirm the ...
- Q89. Which is a PRINCE2 time-driven control?
- Q90. Which statement about time-driven controls is CORRECT?...
- Q91. What is the first task of product-based planning?...
- Q92. What should be considered when defining the number of management stages in a project?...
- Q93. Which is a typical core activity within configuration management?...
- Q94. Which is a minimum requirement when applying the business case theme?...
- Q95. Which is an objective of the Closing a Project process?...
- Q96. What product would enable the Project Manager to review how a Work Package is performing a...
- Q97. What is used to identify any organization or interested party who needs to be informed of ...
- Q98. What is the first task of product-based planning?...
- Q99. Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier enviro...
- Q100. Which role is responsible for creating Checkpoint Reports?...
- Q101. Which is an objective of the 'initiating a project' process?...
- Q102. Which characteristic of a project reflects that there are different perspectives and motiv...
- Q103. Which is performed as part of the recommended risk management procedure?...
- Q104. Identify the missing word in the following sentence. The risk response type [ ? ] can be u...
- Q105. What theme estimates the cost of delivering the project?...
- Q106. Identify the missing words in the following sentence. Project assurance personnel [ ? ] th...
- Q107. Identify the missing word in the following sentence. The purpose of the [?] theme is to id...
- Q108. Which is a type of issue?
- Q109. Which enables the project's products and all interdependencies to be clearly identified an...
- Q110. Which role is responsible for the management of a risk assigned to it?...
- Q111. Which is a purpose of an Issue Report?
- Q112. Which PRINCE2 principle is being applied when tolerances are set for the three levels of p...
- Q113. Which describes an off-specification?
- Q114. Which is an objective of the 'directing a project' process?...
- Q115. What process provides information on a team's work to the project manager?...
- Q116. Which is a purpose of a project brief?
- Q117. What action is taken as part of the 'controlling a stage' process? 1. Create an exception ...
- Q118. According to the 'defined roles and responsibilities' principle, how many categories of st...
- Q119. Which plan provides the Business Case with costs during the Initiating a Project process?...
- Q120. Which of the following statements about lines of authority and reporting are true? 1, The ...
- Q121. Which is a purpose of a quality register?
- Q122. In a commercial environment, which process links the team manager and the PRINCE2 method u...
- Q123. Identify the missing word in the following sentence relating to one of the principles: A P...
- Q124. Which is NOT an objective of the Controlling a Stage process?...
- Q125. Which management product is used to record relationships between specialist products?...
- Q126. Identify the missing words in the following sentence. PRINCE2 requires that the business c...
- Q127. Identify the missing words in the following sentence. The project manager [ ? ] for day-to...
- Q128. Which is an objective of the 'starting up a project' process?...
- Q129. Which does NOT reflect the PRINCE2 principle of continued business justification?...
- Q130. Which role is part of the project management team?...
- Q131. How does the project plan help to support the 'manage by stages' principle?...
- Q132. From whom does a Team Manager obtain approval for a completed product?...
- Q133. Why is the 'initiating a project' process used?...
- Q134. What process is used by the Project Manager to maintain focus on delivery of a stage's pro...
- Q135. Which is a purpose of the 'closing a project' process?...
- Q136. Which should be used to document any uncompleted work that needs to be done to a project p...
- Q137. Who should act as the communication channel between a project and corporate or programme m...
- Q138. Which is a purpose of a lessons log?
- Q139. How is a Benefits Review Plan used in the Closing a Project process?...
- Q140. Which is one of the six aspects of project performance that needs to be managed?...
- Q141. Who represents the three project interests on a project?...
- Q142. In what process is the authorization to deliver the project's products given?...
- Q143. Which is an objective of the 'starting up a project' process?...
- Q144. Which is an objective of the Directing a Project process?...
- Q145. What may be funded from a risk budget?
- Q146. Which role is responsible for the quality of the specialist products delivered in the proj...
- Q147. Identify the missing words in the following sentence. The 'managing a stage boundary' proc...
- Q148. Which of the following statements about stakeholders are true? 1 . Someone who thinks they...
- Q149. Why is a Project Brief produced?
- Q150. Which is a recommended quality review team role?...
- Q151. Which is part of quality control?
- Q152. Who should use the information in a Lessons Report to refine, change and improve the stand...
- Q153. What theme establishes the mechanisms to judge whether a project is worthwhile investing i...
- Q154. What product would enable the Project Manager to review how a Work Package is performing a...
- Q155. Which is a FALSE statement about technical stages?...
- Q156. Which of the following statements about customer's quality expectations and acceptance cri...
- Q157. In which process is the work to be done assigned to a team manager?...
- Q158. Which is NOT a type of issue?
- Q159. What do customer's quality expectations identify?...
- Q160. Which describes a characteristic of a project?...
- Q161. Which is a factor when deciding the duration of a management stage?...
- Q162. Which is a benefit of using PRINCE2?
- Q163. According to the 'tailor to suit the project' principle, what is the basis for effective p...
- Q164. Which is a key decision made during the 'directing a project' process?...
- Q165. Which is a minimum requirement for applying the plans theme?...
- Q166. Which is NOT undertaken during the Initiating a Project process?...
- Q167. Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] w...
- Q168. When should the level of tailoring be defined?...
- Q169. Which role is responsible for specifying the project benefits?...
- Q170. Which PRINCE2 principle helps to address a concern that the project team may NOT have work...
- Q171. How many roles make up the Project Board?
- Q172. What product would enable the Project Manager to review how a Work Package is performing a...
- Q173. What information about benefits management must be documented to meet the minimum requirem...
- Q174. Which of the following is the Business Case used for during the Managing a Stage Boundary ...
- Q175. What should the benefits management approach define?...
- Q176. Which should be funded by a change budget?
- Q177. Which is the base product against which the Project Board can assess progress, issues and ...
- Q178. Which PRINCE2 principle is supported by the setting of tolerances for the three levels of ...
- Q179. Which is a purpose of the plans theme?
- Q180. Which statement describes the Implement' step within the recommended risk management proce...
- Q181. Which is an objective of the Closing a Project process?...
- Q182. What is the project manager role responsible for?...
- Q183. Which describes a characteristic of a project?...
- Q184. Which is a purpose of the plans theme?
- Q185. Which of the following can be done to control the size of the Project Board on a project t...
- Q186. Which role is responsible for the management of a risk assigned to it?...
- Q187. What is the first task of product-based planning?...
- Q188. What needs to be in place to ensure effective issue and change control?...
- Q189. From whom does a Team Manager obtain approval for a completed product?...
- Q190. Which is a type of issue?
- Q191. Which product summarizes progress and is used to decide whether to amend the project scope...
- Q192. Which process is used to define how baselines will be established and controlled?...
- Q193. Which is a purpose of the Quality theme?
- Q194. Identify the missing word in the following sentence. A project's [ ? ] are the measurable ...
- Q195. Why is a project brief produced?
- Q196. If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager repo...
- Q197. Which should be funded from a change budget?
- Q198. Which is an objective of the 'directing a project' process?...
- Q199. Which describes an off-specification?
- Q200. Which is a purpose of a Product Description?
- Q201. Identify the missing words in the following sentence. A Change Authority may be given a [?...
- Q202. According to PRINCE2, why might there be more than one business case for a project?...
- Q203. Identify the missing word(s) in the following sentence. During a quality review meeting [ ...
- Q204. Identify the missing words in the following sentence. The role of [ ? ] is responsible for...
- Q205. Which process is used by a Team Manager to coordinate work on one or more of the project's...
- Q206. What is documented in the project plan to support the 'manage by exception' principle?...
- Q207. Which is one of the six aspects of project performance that needs to be managed?...
- Q208. The application of which principle helps to define what should be included in a project?...
- Q209. Which statement is true for ALL project stakeholders?...
- Q210. Which is a key decision made during the 'directing a project' process?...
- Q211. What is the first task of product-based planning?...
- Q212. Which is a minimum requirement for applying the organization theme?...
- Q213. What needs to be in place to ensure effective issue and change control?...
- Q214. Which describes a risk event?
- Q215. To meet the minimum requirements for applying the progress theme, what must be considered?...
- Q216. What should the benefits management approach define?...
- Q217. What theme provides all management levels within the project management team with mechanis...
- Q218. Which is an objective of the quality review technique?...
- Q219. Which product defines how the project board should approve the management products produce...
- Q220. Identify the missing words in the following sentence. An objective of the Directing a Proj...
- Q221. Which is a purpose of a Project Brief?
- Q222. Which is a purpose of the plans theme?
- Q223. Which describes risk appetite?
- Q224. Which is a minimum requirement for applying the change theme?...
- Q225. Which is a purpose of the Managing Product Delivery process?...
- Q226. Who carries out audits that are independent of the project?...
- Q227. Which task is performed by the Change Authority?...
- Q228. Which product records any project outcomes perceived as negative by stakeholders?...
- Q229. Which statement applies to Stage Plans?
- Q230. Which action should the project manager take during the 'assessing issues' step?...
- Q231. Which of the following statements about customer's quality expectations and acceptance cri...
- Q232. Which is a purpose of the 'controlling a stage' process?...
- Q233. Who should act as the communication channel between a project and corporate or programme m...

[×]
Download PDF File
Enter your email address to download PRINCE2.PRINCE2-Foundation.v2023-06-02.q233.pdf