Question 61/61
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
Correct Answer: D
Add Comments
- Other Question (61q)
- Q1. How can you update the degree of processing for an activity?...
- Q2. Project structure. You intent to work with predefined project coding mask to create projec...
- Q3. You want to use subnetworks during the project. Which of the following statements describe...
- Q4. How are earliest dates and latest dates of activities scheduled?...
- Q5. A customer needs to analyse the capacity requirements of their network activities. Which r...
- Q6. You have assigned a material to a network activity and want to determine the requirement d...
- Q7. Project Structures You want to enable user fields for customer project. Therefore you crea...
- Q8. How can you confirm the working hours of different work centers for a single activity?...
- Q9. What is the reason for assigning billing plans in customer projects?...
- Q10. Cost & Budget You are using network and internal activities in your project . You have...
- Q11. Which of the following is used to plan basic dates manually for WBS elements? Choose the c...
- Q12. Which sales documents can update planned revenues on WBS elements? Note: There are 2 corre...
- Q13. Which of the following actions can transfer actual costs for external processing? Note: Th...
- Q14. Cost & budget A service Company use project management and they complain that the syst...
- Q15. What is the reason for assigning billing plans in customer projects?...
- Q16. A service company uses project management and they complain that the system does not preve...
- Q17. What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to ...
- Q18. Material Your customer uses Progress Tracking for network components and mantains dates of...
- Q19. You have activated the workflow for confirmation variances in SAP Project System. Who is t...
- Q20. A component is assigned to a network activity. What are the prerequisites to generate proj...
- Q21. Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct An...
- Q22. The__________________that you specify when you create a project definition is unique for t...
- Q23. COST AND BUDGET You have assigned a budget to WBS element with your project What budget fu...
- Q24. Project Structure Which statement regarding the creation of a new work breakdown structure...
- Q25. You are using WBS elements and activities are NOT assigned. Which statements apply to the ...
- Q26. You used reductions to reduce the scheduled duration of all internally-processed activitie...
- Q27. You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Custo...
- Q28. Project structure You want use a template to create a new project with network in the Proj...
- Q29. Cost and budget A customer works in a multinivel production environment with bill of mater...
- Q30. The basic dates of subordinate WBS elements should be extrapolated without taking into acc...
- Q31. Dates You have a project with a network, material and milestone. You want to plan an activ...
- Q32. Your customer's projects are subject to recurring changes of date. The assembly activity h...
- Q33. Which report can use user-specific layouts?
- Q34. You want to determine the planned costs for an internally processed activity. Which data d...
- Q35. Dates How are earliest dates and latest dates of activities schedule?...
- Q36. You are using budgeting and active availability control. How can availability control be a...
- Q37. In your logistics project, you want to carry out the internal project work as soon as poss...
- Q38. What could be a reason to use expert mode in the valuation method for results analysis?...
- Q39. Your customer has created networks with internal activities and generated capacity require...
- Q40. What could be a reason to use expert mode in the valuation method for results analysis?...
- Q41. An external component is assigned to a network activity. The delivery date for the purchas...
- Q42. In your project, you work with a network and external activities. You have created a purch...
- Q43. A customer needs to analyze the capacity requirements of their network activities. Which r...
- Q44. To which object can you assign a factory calendar?...
- Q45. You are using budgeting and active availability control. How can availability control be a...
- Q46. What are the prerequisites for delivering materials from the project? Note: There are 2 co...
- Q47. Revenues & Payment Your customer wants to plans and post revenues for WBS elements. Wh...
- Q48. Which of the following statements apply to project versions? Note: There are 2 correct Ans...
- Q49. Material You want to create purchase requisition for the material used in your project. Ho...
- Q50. Project Structure Your customer has implemented budgeting for projects. The current budget...
- Q51. Which statements describe planned and actual revenue for WBS elements? Note: There are 2 c...
- Q52. Which objects can be used to specify settlement rules? Note: There are 2 correct Answers t...
- Q53. Resources How are capacity requirements determined?...
- Q54. Cost & Budget. A customer wants to allocate overhead rates to a WBS element. What must...
- Q55. You have created an internally-processed network activity, and assigned a work center and ...
- Q56. The individual tasks in the project are mapped as activities in a WBS. Determine whether t...
- Q57. Which object is used to allocate the costs from a claim to the project structure?...
- Q58. What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: T...
- Q59. How can you record external service activities with service master data? Note: There are 2...
- Q60. Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note:...
- Q61. You plan an activity that starts on February 1 and finishes on February 28. For this activ...