Question 51/59
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well.
Now, you increase the quantity of the external activity. How does the system support this scenario?
Now, you increase the quantity of the external activity. How does the system support this scenario?
Correct Answer: D
Add Comments
- Other Question (59q)
- Q1. Project Structure Your customer has implemented budgeting for projects. The current budget...
- Q2. The basic dates of subordinate WBS elements should be extrapolated without taking into acc...
- Q3. The various work packages in the project are described as individual______________. Choose...
- Q4. Which of the following data can be maintained in a standard network? Note: There are 3 cor...
- Q5. The__________________that you specify when you create a project definition is unique for t...
- Q6. You want to determine the planned costs for an internally processed activity. Which data d...
- Q7. A customer needs to analyse the capacity requirements of their network activities. Which r...
- Q8. How can you confirm the working hours of different work centers for a single activity?...
- Q9. You want to create a reservation for a material component assigned to a network activity. ...
- Q10. Revenues & Payment Your customer wants to plans and post revenues for WBS elements. Wh...
- Q11. How can you search in the structure overview based on the user status? Note: There are 2 c...
- Q12. You used reductions to reduce the scheduled duration of all internally-processed activitie...
- Q13. What are some of the advantages of using project simulations? Note: There are 3 correct An...
- Q14. Dates How are earliest dates and latest dates of activities schedule?...
- Q15. What is the reason for assigning billing plans in customer projects?...
- Q16. Which of the following factors influence the scheduling of internal processing activities?...
- Q17. Float time is calculated during scheduling. Which of the following statements about float ...
- Q18. How can you record external service activities with service master data? Note: There are 2...
- Q19. What are some of the possible functions in user status profiles? Note: There are 2 correct...
- Q20. You have activated the workflow for confirmation variances in SAP Project System. Who is t...
- Q21. You want to create a reservation for a material component assigned to a network activity. ...
- Q22. Float time is calculated during scheduling. Which of the following statements about float ...
- Q23. What functions are available for period end closing in SAP Project System? Note: There are...
- Q24. Resources You Want assign milestone to WBS element? For what can you use these milestone....
- Q25. Which object is relevant in assembly processing to create an assembly order for the SD doc...
- Q26. What could be a reason to use expert mode in the valuation method for results analysis?...
- Q27. Your customer wants to use requirements grouping in SAP Project System. What are the prere...
- Q28. Project Structures You are using assembly processing. You need to determine the delivery d...
- Q29. Which of the following business processes do NOT lead to the booking of actual costs to an...
- Q30. Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to...
- Q31. Cost and Budget What function are available for period end-closing in the project System?...
- Q32. You have assigned a budget to WBS elements within your project. What function can be used ...
- Q33. You are using budgeting and active availability control. How can availability control be a...
- Q34. Which report can use user-specific layouts?
- Q35. For which objects can billing plans be created? Note: There are 2 correct Answers to this ...
- Q36. You want to make sure that certain tasks must start on a given date. Where can you maintai...
- Q37. Which object is relevant in assembly processing to create an assembly order for the SD doc...
- Q38. Which objects can be used to specify settlement rules? Note: There are 2 correct answers t...
- Q39. You use networks and internal activities in your project. You have activated capacity requ...
- Q40. Which of the following business processes do NOT lead to the booking of actual costs to an...
- Q41. Which statements describe planned and actual revenue for WBS elements? Note: There are 2 c...
- Q42. Cost & Budget. A customer wants to allocate overhead rates to a WBS element. What must...
- Q43. Which organizational structures are required for network activities? Note: There are 3 cor...
- Q44. Which object is used to allocate the costs from a claim to the project structure?...
- Q45. In your logistics project, you want to carry out the internal project work as soon as poss...
- Q46. You want to allocate overhead rates to a WBS element. What must you assign to the WBS elem...
- Q47. Project Structures You want to enable user fields for customer project. Therefore you crea...
- Q48. How are earliest dates and latest dates of activities scheduled?...
- Q49. How can you grant individual authorization for WBS elements and networks?...
- Q50. Materials Your customer use a tight (estrecha) integration between sales order and WBS wit...
- Q51. In your project. You work with a network and external activities. You have created a purch...
- Q52. What is the reason for assigning billing plans in customer projects?...
- Q53. Which sales documents can update planned revenues on WBS elements? Note: There are 2 corre...
- Q54. Which of the following actions can transfer actual costs for external processing? Note: Th...
- Q55. Which of the following is used to plan basic dates manually for WBS elements? Choose the c...
- Q56. Your customer wants to use requirements grouping in SAP Project System. What are the prere...
- Q57. What are the prerequisites for resource-related billing? Note: There are 2 correct Answers...
- Q58. What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: T...
- Q59. In your logistics project you want to carry out the internal project work as soon as possi...