Question 1/96
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.
How can you define external task in your project.
Note : there are 2 correct answers for this question.
Correct Answer: B,D
"You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers." Reference: 4
Add Comments
- Other Question (96q)
- Q1. Resources How can you define external task in your project. Note : there are 2 correct ans...
- Q2. You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Custo...
- Q3. Where do you maintain the length of the project ID?...
- Q4. You have created an internally-processed network activity, and assigned a work center and ...
- Q5. Project Structure You plan double the work on each internal activity for multiple project....
- Q6. Your customer wants to use requirements grouping in SAP Project System. What are the prere...
- Q7. COST AND BUDGET You have assigned a budget to WBS element with your project What budget fu...
- Q8. You have assigned a material to a network activity and want to determine the requirement d...
- Q9. Your customer wants to use requirements grouping in SAP Project System. What are the prere...
- Q10. Which of the following factors influence the scheduling of internal processing activities?...
- Q11. Resources How are capacity requirements determined?...
- Q12. The basic dates of subordinate WBS elements should be extrapolated without taking into acc...
- Q13. You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Custo...
- Q14. What are the prerequisites for resource-related billing? Note: There are 2 correct answers...
- Q15. The system status of a WBS element is created (CRTD). Which business process is allowed fo...
- Q16. Which of the following statements are true? Choose the correct answers. There are 2 correc...
- Q17. Which organizational structures are required for network activities? Note: There are 3 cor...
- Q18. Cost & budget A service Company use project management and they complain that the syst...
- Q19. You want to use subnetworks during the project. Which of the following statements describe...
- Q20. Project Structure Your customer has implemented budgeting for projects. The current budget...
- Q21. You have saved a network and activates with assigned material components. As soon as you r...
- Q22. When you create a service activity in your network, what data can be entered? Note: There ...
- Q23. Cost & budget A service Company use project management and they complain that the syst...
- Q24. Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note:...
- Q25. What functions are available for period end closing in SAP Project System? Note: There are...
- Q26. You are working with networks and WBS elements. Which of the following statements applies?...
- Q27. You want to use subnetworks during the project. Which of the following statements describe...
- Q28. Where can you define a network as "header-account-assigned" or "activity-account-assigned"...
- Q29. Cost and Budget What function are available for period end-closing in the project System?...
- Q30. Which sales documents can update planned revenues on WBS elements? Note: There are 2 corre...
- Q31. Which statements describe planned and actual revenue for WBS elements? Note: There are 2 c...
- Q32. Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct ans...
- Q33. Material You want to create purchase requisition for the material used in your project. Ho...
- Q34. Dates How are earliest dates and latest dates of activities schedule?...
- Q35. A customer needs to analyze the capacity requirements of their network activities. Which r...
- Q36. You want to create a reservation for a material component assigned to a network activity. ...
- Q37. Your customer has created networks with internal activities and generated capacity require...
- Q38. You have created an internally-processed network activity, and assigned a work center and ...
- Q39. Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct ans...
- Q40. Your customer has created networks with internal activities and generated capacity require...
- Q41. You want to determine the planned costs for an internally processed activity. Which data d...
- Q42. Where do you maintain the length of the project ID?...
- Q43. How can you grant individual authorization for WBS elements and networks?...
- Q44. In your project, you work with a network and external activities. You have created a purch...
- Q45. Materials Your customer want to use scheduling for network to specify planned dates of tas...
- Q46. What are some of the advantages of using project simulations? Note: There are 3 correct An...
- Q47. A customer needs to analyze the capacity requirements of their network activities. Which r...
- Q48. Float time is calculated during scheduling. Which of the following statements about float ...
- Q49. In your logistics project you want to carry out the internal project work as soon as possi...
- Q50. Which statements describe planned and actual revenue for WBS elements? Note: There are 2 c...
- Q51. You want to create purchase requisition for the material used in your project. However aft...
- Q52. For which objects can billing plans be created? Note: There are 2 correct Answers to this ...
- Q53. Which of the following data can be maintained in a standard network? Note: There are 3 cor...
- Q54. Project Structures You want to enable user fields for customer project. Therefore you crea...
- Q55. You want to make sure that certain tasks must start on a given date. Where can you maintai...
- Q56. To which object can you assign a factory calendar?...
- Q57. Materials Your customer use a tight (estrecha) integration between sales order and WBS wit...
- Q58. You want to assign milestones to WBS elements. For what can you use these milestones? Note...
- Q59. You want to use billing for a customer project. Which customizing object controls the bill...
- Q60. You have created an internally-processed network activity, and assigned a work center and ...
- Q61. Which of the following factors influence the scheduling of internal processing activities?...
- Q62. Material How can the system activate requirements (such as reservations or purchase requis...
- Q63. Your costumer Project/planning Board to create/update Gant charts. Which the following are...
- Q64. Project Structure Your customer has implemented budgeting for projects. The current budget...
- Q65. Budgeting is implemented for projects. The budget has been adjusted several times. What st...
- Q66. The various work packages in the project are described as individual______________. Choose...
- Q67. You use networks and internal activities in your project. You have activated capacity requ...
- Q68. An external component is assigned to a network activity. The delivery date for the purchas...
- Q69. You want to allocate overhead rates to a WBS element. What must you assign to the WBS elem...
- Q70. Resources Which of the following transactions can you use to post actual cost for external...
- Q71. You want to make sure that certain tasks must start on a given date. Where can you maintai...
- Q72. Your customer's projects are subject to recurring changes of date. The assembly activity h...
- Q73. How are earliest dates and latest dates of activities scheduled?...
- Q74. Dates How are earliest dates and latest dates of activities schedule?...
- Q75. Which of the following statements apply to project versions? Note: There are 2 correct Ans...
- Q76. In your project. You work with a network and external activities. You have created a purch...
- Q77. You have activated the workflow for confirmation variances in SAP Project System. Who is t...
- Q78. How can you search in the structure overview based on the user status? Note: There are 2 c...
- Q79. The individual tasks in the project are mapped as activities in a WBS. Determine whether t...
- Q80. Cost & Budget You are using network and internal activities in your project . You have...
- Q81. A customer needs to analyse the capacity requirements of their network activities. Which r...
- Q82. You use networks and internal activities in your project. You have activated capacity requ...
- Q83. Which of the following factors influence the scheduling of internal processing activities?...
- Q84. Which of the following is used to plan basic dates manually for WBS elements? Choose the c...
- Q85. Where do you control whether a project stock is managed as valuated or non-valuated projec...
- Q86. In your logistics project, you want to carry out the internal project work as soon as poss...
- Q87. Which of the following is used to plan basic dates manually for WBS elements? Choose the c...
- Q88. Where can you assign the use status profile for WBS elements? Note: There are 3correct ans...
- Q89. Which planning method can prevent further rescheduling of activities?...
- Q90. You are using budgeting and active availability control. How can availability control be a...
- Q91. Which of the following business processes do NOT lead to the booking of actual costs to an...
- Q92. Which statement is valid regarding networks? Note: There are 2 correct Answers to this que...
- Q93. You used hierarchical revenue planning to plan revenues for WBS elements manually. The cos...
- Q94. You want to determine the planned costs for an internally processed activity. Which data d...
- Q95. Float time is calculated during scheduling. Which of the following statements about float ...
- Q96. You want to use subnetworks during the project. Which of the following statements describe...