Which statement is NOT true about the Reservations tab?
Correct Answer: E
In Oracle Manufacturing Cloud, the Reservations tab provides detailed information on reservations linked to work orders and sales orders. The following explains why statement E is not true:
Statement E is incorrect: A work order is typically viewed as a source of supply, not demand. Sales orders generate demand, while work orders are created to supply the required products. Therefore, reservation details will show the work order as a source of supply and the sales order as the source of demand.
Correct statements:
Statement A: Demand details such as document type (e.g., Sales Order), customer number, document number, due date, and quantity are displayed.
Statement B: Reservations are often created for Back-to-Back or Configured Items sales orders to ensure the necessary products are reserved in the system for production.
Statement C: A work order can be reserved against one or more sales orders, especially in cases of configurable or customized items.
Statement D: Manual reservations for a work order can be made directly in inventory to allocate the necessary materials for production.
Statement E is incorrect: A work order is typically viewed as a source of supply, not demand. Sales orders generate demand, while work orders are created to supply the required products. Therefore, reservation details will show the work order as a source of supply and the sales order as the source of demand.
Correct statements:
Statement A: Demand details such as document type (e.g., Sales Order), customer number, document number, due date, and quantity are displayed.
Statement B: Reservations are often created for Back-to-Back or Configured Items sales orders to ensure the necessary products are reserved in the system for production.
Statement C: A work order can be reserved against one or more sales orders, especially in cases of configurable or customized items.
Statement D: Manual reservations for a work order can be made directly in inventory to allocate the necessary materials for production.
Add Comments
- Other Question (18q)
- Q1. In a manufacturing plant, two purchase components, PI and P2, and a resource, Rl, are requ...
- Q2. You have been asked to set up cost estimates for 10 different purchased items. Which two t...
- Q3. Which three requirements are fulfilled by nonstandard work orders?...
- Q4. Your customer runs two daily shifts in their plant: morning shift and evening shift. A res...
- Q5. Which statement is NOT true about the Reservations tab?...
- Q6. Your client has asked you to implement the functionality to ensure that the system checks ...
- Q7. Two work definitions are created in the application: one for Engine Finished Good and the ...
- Q8. Your client informs you that after running the "Process Item Structure Changes to Work Def...
- Q9. The pick release of a project work order creates movement requests with the project and th...
- Q10. In which three ways does Supply Chain Orchestration enrich supply requests with project de...
- Q11. Which statement is NOT true about user-defined work order statuses?...
- Q12. In a Manufacturing Cloud implementation, users are finding it difficult to track informati...
- Q13. Your client needs to implement operational checks for compliance with training and job req...
- Q14. In the work execution area, which three infolets are provided to users for instant access?...
- Q15. Which two reports provide work order cost-related information to Costing users?...
- Q16. Which three statements are true about managing Units of Measure?...
- Q17. Your client is planning to override the Plant Production Calendar with One or More Date-Ef...
- Q18. Which option represents all the production exception types that can be reported by a Produ...